2023 Construction Law Compendium (Florida)
This 2023 Compendium update was designed to serve as a single resource regarding important construction law issues.
I.
Mechanic’s Lien Basics
Generally, the term “mechanic’s
lien,” refers to a lien granted by law for the purpose of obtaining priority of
payment for the price or value of work performed or materials furnished for
fixing or improving something. Florida
law recognizes different classes of liens: those created by statute for
improving things such as machines, crops, timber, animals, cotton ginning, and
other things;[1]
and construction liens for labor, services, and materials furnished in
improving real property.[2]
All are governed by a detailed statutory scheme under Chapter 713, Florida
Statutes (2019).
As a result of a 1989 commission on the study of mechanic’s
lien law, the Florida Legislature changed the name of liens placed on real
property arising out of improvement of the property from “mechanic’s liens” to
“construction liens,” effective January 1, 1991.
A.
Requirements
To claim a construction lien in Florida, certain procedural
requirements must be satisfied, and, while compliance with these procedures is important,
Florida courts generally apply a liberal construction favoring the lien-holding
contractor or laborer.[3]
Foremost, a construction lien must arise from an agreement
between the lienor and another party. A written or oral agreement will support
a construction lien; however, contracts implied-in-law will not, so a
construction lien must be based upon either an express or implied-in-fact
contract.[4]
Further, construction liens only apply to privately owned property.[5]
While improvements made to property under a private lease on government land
are lienable, a separate remedy applies for property owned by the government.[6]
The security for a construction lien depends upon the
right, title, and interest of the person contracting for improvements.[7] Naturally, if the property is held in fee simple,
the entire interest of the property owner will be subject to the construction
lien. When property is owned in joint ownership or as a leasehold, the scope of
the lien is usually commensurate with the rights and interests of the party
contracting for the improvements. If a lessee contracts for improvements, the
lessor’s interest will not be subject to the lien if the lease contains
language that prohibits lien liability and the landlord records either a copy
of the lease, a short form memorandum of the lease, or a notice in the public
records of the county in which the property is located.[8]
Both persons and entities involved in construction or
repair of real property have lien rights under the Florida lien law.[9] These parties include laborers,[10] materialmen,[11]
contractors,[12]
subcontractors,[13]
sub-subcontractors,[14]
subdivision improvers,[15]
and professional lienors.[16]
Unlicensed contractors, however, are not permitted to enforce their contracts
or to obtain the benefits of a construction lien.[17]
As noted above, adherence to the procedural provisions of
the construction lien statute are critical to enforcement.[18] Chronologically, the first document to be
recorded for a construction lien is usually the notice of commencement.[19] A
notice of commencement must be recorded before the start of construction (or
the recommencing completion of any improvement after a default), and the
improvements described must be commenced within ninety (90) days after its
recording, or the notice is void.[20] Notably, even when commencement timely occurs,
the notice itself—unless specifically indicated or amended—remains valid for
only one (1) year.[21] A
notice of commencement must specifically include details of the improvement
project, all of which are expressly incorporated into the statute within a
standard form.[22]
Next, a notice to owner should be served before the lienor
commences furnishing labor, services, or materials.[23]
The notice may be served up to forty-five (45) days after the lienor commences
his or her services but must, in any event, be served before the owner makes
final payment in reliance upon a final contractor’s affidavit.[24]
With the exception of design professionals, who are exempt from this
requirement,[25]
failure to serve a notice to owner is a complete defense to enforcement of a
lien by any person.[26]
The party seeking to file the lien may do so during the
performance of their work or during the furnishing of materials on the property
or improvement to be liened.[27] However,
all claims of lien must be recorded within ninety (90) days of the last date
upon which the lienor furnished labor, services or materials or the date of the
prime contractor’s default for a lienor claiming through the prime contractor,
whichever occurs first.[28]
B.
Enforcement and Foreclosure
Suit to enforce a construction lien must be filed no later
than one (1) year from the date of recording[29]
unless this period is shortened by a notice of contest of lien[30]
or by service of a summons to show cause.[31] As an action to foreclose a lien is an in
rem proceeding, it must be brought in the county (or federal district)
where the property or other security for the lien is situated.[32]
The property owner is a indispensable party to an action to foreclose a
construction lien,[33]
and when property is owned by a couple, both spouses are indispensable parties
regardless of whether both or only one signed the contract for improvements.[34]
As a general principle of equity and public policy to avoid
multiplicity of suits, a contractor is generally entitled to join its unpaid
subcontractors and suppliers in an action to enforce a lien.[35]
However, neither a contractor nor subcontractor is not an indispensable party
to an action by any other subcontractor and/or supplier to enforce a lien
against an owner.[36]
The prevailing party in an action to enforce a construction
lien is entitled to recover its attorneys’ fees and costs.[37] However,
the prevailing party generally must prevail on all the ‘significant issues,’
not merely a successful defense or foreclosure on the lien claim alone.[38] Also, a property owner may also seek
entitlement to attorneys’ fees for a fraudulently filed lien.[39] A
successful lienor is also entitled to recover pre-judgment interest in addition
to the amount of the lien.[40]
Further, construction lien rights are cumulative to any other rights and
remedies a lienor may have.[41]
Therefore, actions for breach of contract, open account, account stated, goods
sold and delivered, or any other remedial relief available may be sought in
conjunction or in addition to enforcement of a construction lien. This further may also include entitlement to
additional finance charges arising from the subcontractor or suppliers’
contract with another contractor in the privity chain.[42] A
lienor may also settle and satisfy a construction lien against an owner and
retain rights to pursue the balance against a lienor’s customer.
C.
Ability to Waive and Limitations on Lien
Rights
The right to claim a construction lien cannot be
waived in advance either by contract, agreement, or any other method; in other
words, a lien right may be waived only to the extent of services that have
already been furnished.[43]
Any waiver of the right to claim a lien made in advance is unenforceable under
Florida law.[44] Forms for waiver and release of lien upon
progress and final payment are expressly incorporated into the statutory
language and have been specifically upheld by the courts.[45]
II.
Public Project Claims
Constitutional restraints prohibit pledging public-owned
land for debt without having an election. As these constitutional issues make
lien law impractical for publicly owned property, Florida law provides for
statutory payment (and performance) bonds for the purpose of protecting the
general contractor, owner, and the public as well as laborers, material
suppliers, and subcontractors on projects where these persons are unable to
acquire construction liens.
A.
State and Local Public Work
Florida law requires the successful bidder for Florida
Department of Transportation (“FDOT”) construction or maintenance contracts to
provide a payment and performance bond in an amount equal to the awarded
contract price.[46]
For other governmentally owned construction projects, Florida’s “Little Miller
Act,” section 255.05, Florida Statutes, requires any person entering into a
contract with any state, county, city, or political subdivision thereof to
execute and record a payment and performance bond.[47]
i.
Notices and Enforcement
Section 337.18, Florida Statues, sets forth bond
requirements for construction or maintenance performed pursuant to FDOT
contracts, which begins by mandating that any contractor required to furnish a
payment and performance bond under the section to maintain a copy of the bond
at its principal place of business and at the job-site office.[48]
Any claimant who is not in privity with the contractor for an FDOT project,
must provide written notice that he or she intends to look to the bond for
protection no later than ninety (90) days after first furnishing labor,
materials, or supplies for the project.[49]
After not receiving payment for his or her labor, services, or materials, a
claimant must deliver to the contractor and to the surety written notice of
performance and nonpayment.[50]
This notice of nonpayment may not be served earlier than forty-five (45) days
after first furnishing labor, materials, or supplies for the project, or later
than ninety (90) days after final furnishing of labor, materials, or supplies
by the claimant.[51]
A section 337.18 bond claimant has a right of action
against both the contractor and the surety for the amount due to him or her,
including unpaid finance charges due under the claimant’s contract.[52]
Further, the prevailing party in an action to enforce a claim against a payment
bond under section 337.18 is entitled to recover attorneys’ fees and costs.[53]
Any action on the bond must be instituted by a claimant against the contractor
or surety within 365 days after the final acceptance of the contract work by
the department, but such action may not involve FDOT.[54]
Section 255.05, Florida Statutes, sets forth bond
requirements for governmental contracts other than FDOT work. Under this
section any person entering into a contract with any state, county, city, or
political subdivision thereof must first record its payment and performance
bond in the public record of the county where the improvement is located,[55]
and before commencing work, the contractor must provide the public entity a
certified copy of the recorded bond.[56] A
claimant who is not in privity with the contractor for work performed pursuant
these governmental contracts must provide written notice that he or she intends
to look to the bond for protection no later than forty-five (45) days after
first furnishing labor, materials, or supplies for the project.[57]
After not receiving payment for his or her labor, services, or materials, a
claimant must deliver to the contractor and to the surety written notice of
performance and nonpayment.[58]
This notice of nonpayment may not be served earlier than forty-five (45) days
after first furnishing labor, materials, or supplies for the project, or later
than ninety (90) days after final furnishing of labor, materials, or supplies
by the claimant.[59]
An action for labor, materials, or supplies provided, but not paid for, may not
be instituted against the contractor or the surety unless the notice to the
contractor and notice of nonpayment have been served.[60] A
section 255.05 bond claimant has a right of action against both the contractor
and the surety for the amount due to him or her, including unpaid finance
charges due under the claimant’s contract.[61]
The prevailing party in an action to enforce a claim against a payment bond
under section 255.05 is further entitled to recover attorneys’ fees and costs.[62]
Any action must be instituted against the contractor or the surety on the
payment bond within one (1) year after the performance of the labor or
completion of delivery of the materials or supplies, but such action may not
involve the public authority.[63]
B.
Claims to Public Funds
Not applicable in Florida.
III.
Statutes of Limitation and Repose
A.
Statutes of Limitation and Limitations on
Application of Statutes
An action founded on the design, planning, or construction
of an improvement to real property must be brought within four (4) years from
the date of actual possession by the owner, the date of issuance of a
certificate of occupancy, the date of abandonment of construction if not
completed, or the date of completion or termination of the contract between the
professional engineer, registered architect, or licensed contractor[64]
and his or her employer, whichever date is latest.[65] However,
if an action concerns a latent defect, the time runs from the time the defect
is first discovered, or should have been discovered with the exercise of due
diligence.[66]
The 2018 Legislature added two provisions to this statute
of limitations, which apply to any action commenced on or after July 1, 2018,
regardless of when the cause of action accrued.[67]
First, a provision allowing any counterclaims, cross-claims, and third-party
claims arising out of the conduct, transaction, or occurrence set out in a
pleading to be commenced up to one (1) year after service of the pleading to
which such claims relate, regardless of whether these newly asserted claims
would otherwise be time barred.[68]
Second, a provision designating that correction or repairs performed on
construction which is within the scope of a duly issued building permit and
final certificate of occupancy or certificate of completion, does not extend
the period of time within which an action must be commenced.[69]
This four- (4) year limitation for actions founded on the design, planning, or
construction of an improvement to real property generally applies to any action
arising out of improvements to real property whether the action is pursued on
the basis of a contract, negligence, violation of a building code, or other
theory of recovery.[70]
In some rare circumstances, claims against design
professionals filed by parties in privity with those professionals will need to
be brought within two (2) years;[71]
however, when there is no direct contract between the professional and the
person injured by professional negligence, the two- (2) year statute does not
apply.[72]
Similarly if the four- (4) year construction defect
limitation does not apply, legal or equitable actions on a written contract are
subject to a five- (5) year statute of limitations;[73]
tort actions (including intentional torts, trespass, fraud, and negligence) and
actions founded on an oral or implied contract are subject to a four- (4) year
statute of limitations;[74]
wrongful death actions are subject to a two- (2) year statute of limitations;[75]
and actions for specific performance or to enforce equitable liens relating to
improvements to real estate are subject to a one- (1) year statute of
limitations.[76]
B.
Statutes of Statute of Repose – 2023 Amendments
to Fla. Stat. § 95.11(3)(c)
A statute of repose
“eliminates the underlying legal right; it precludes the right of action after
a specified period of time…rather than establishing a time period within which
the action must be brought measured from the point in time when the cause of
action accrued.;”[77]
Prior to April
13, 2023, the statute of repose regarding causes of action concerning latent
construction defects was 10 years.[78]
The Act reduces the pre-existing statute of repose that concerns causes of
action pertaining to latent construction defects to 7 years.[79]
Perhaps more
importantly, it should be noted that the amendment to the pre-existing statute
of repose has brought some much-needed clarity as to when the time for the
statute of repose begins to accrue. Under the prior law, there was ambiguity as
to when the time for the statute of repose began. Specifically, the prior
statutory language provided the following:
An action
founded on the design, planning, or construction of an improvement to real
property…must be commenced within 10 years after the date of actual
possession by the owner, the date of the issuance of the certificate of
occupancy, the date of abandonment of construction if not completed, or the
date of completion of the contract or termination of the contract between the
professional engineer, registered architect, or licensed contractor and his or
her employer, whichever date is latest. [80]
Notably, under
current law, the statute of repose period begins to run at the earliest
(rather than the latest) of the following: (1) the issuance or a certificate of
occupancy by the Authority Having Jurisdiction, (2) the issuance of a
certificate of completion by the Authority Having Jurisdiction, (3) the date of
abandonment of construction if not completed.
In addition to
these important changes, there are two further favorable caveats. For
single-dwelling residential buildings that serve as model homes: the time
begins to run from the date that a deed is recorded first transferring title to
another party.[81]
Furthermore, if the improvement of real property consists of the design,
planning, or construction of multiple building each building must be considered
its own improvement for purposes of determining the limitations period set
forth in the section.[82]
While the statute of limitations is statutorily tolled
under certain circumstances, these provisions do not toll the statute of
repose, except as noted within the statue itself.[83] Most recently, the Florida’s Fourth District
Court of Appeal controversially held that the delivery of a Chapter 558
pre-suit notice of alleged construction defects within a townhome complex
“commenced an action” before expiration of the statute of repose, sufficient to
effectively toll and negate its application.[84]
Notably, Florida’s Fifth District Court of Appeal also recently
held that an engineer’s post-construction structural review of a newly
completed residential home did not fall within the context of the 10-year
statute of repose contained within section 95.11(3)(c), Florida Statutes.[85] Even though the engineering review took place
well outside of the 10-year repose period, structural design defects were more recently
discovered by the original owner within the 2-year professional statute of limitation
period.[86] The Court held that the action for
professional engineering negligence was not subject to the 10-year statute of
repose because the reviewing engineer did not design, plan, or construct any
improvement to the real property and thus the action against it was not
“founded on” the design, plan, or construction (turning on the fact that the
improvements were already complete, albeit newly, at the time of the engineer’s
review) necessary to frame it within section 95.11(3)(c).[87]
IV.
Pre-suit Notice of Claim and Opportunity
to Cure
Prior to filing any action alleging construction defects, a
claimant is required under Florida law to comply with statutory pre-suit notice
and opportunity to cure requirements.[88]
Premised upon the Legislature’s belief that it is beneficial to have an
alternative method to resolve construction disputes and aimed both at reducing
the need for litigation as well as protecting the rights of property owners,
these requirements apply to all actions alleging construction defect claims
against contractors, subcontractors, suppliers, and design professionals for
damage to real or personal property.[89]
Giving deference to its statutory namesake, the required
pre-suit notice is commonly referred as a Chapter 558 Notice of Construction
Defects. The Chapter first defines several terms as used within the statutory
scheme. A “claimant” is any “property owner, including a subsequent purchaser
or association, who asserts a claim for damages against a contractor,
subcontractor, supplier, or design professional concerning a construction
defect or a subsequent owner who asserts a claim for indemnification for such
damages.”[90]
However, the term claimant specifically excludes contractors, subcontractors,
suppliers, or design professionals.[91]
An “action” is defined within the Chapter as “any civil action or arbitration
proceeding for damages or indemnity asserting a claim for damage to or loss of
real or personal property caused by an alleged construction defect, but does
not include any administrative action or any civil action or arbitration
proceeding asserting a claim for alleged personal injuries arising out of an
alleged construction defect.”[92]
Further, a “construction defect” is defined to mean any “deficiency in or
arising out of the design, specifications, surveying, planning, supervision,
observation of construction, or construction, repair, alteration, ore
remodeling of real property resulting from” defective materials, products, or
components used in the construction or remodeling, a violation of applicable
building codes, failure of the design to meet applicable professional standards
of care, or failure to construct or remodel real property in accordance with accepted
trade standards for good and workmanlike construction.[93]
Chapter 558 specifically does not bar, limit, or create any
rights or defenses, except as specifically provided within the Chapter.[94] This is often its greatest criticism, as it
does not practically help to resolve many defect claims, if any at all.
However, pursuant to the Chapter, construction defect claimants are not
authorized to file a construction defect action in Florida without first
complying with the pre-suit and notice requirements outlined therein.[95]
Further, to the extent that any arbitration clause conflicts with Chapter 558,
the statute explicitly controls.[96] A
court is required to stay any action, without prejudice, if the claimant filed
the action alleging a construction defect without first fully complying with
the statute.[97]
Specifically, Chapter 558 requires a claimant to serve
written notice of his or her claim on the contractor, subcontractor, supplier
or design professional at least sixty (60) days before filing a lawsuit
alleging construction defects.[98]
If the action involves an association representing more than twenty (20)
parcels, the claimant must serve notice at least one-hundred-twenty (120) days
before filing the action.[99]
The notice “must describe in reasonable detail the nature
of each alleged construction defect and, if known, the damage or loss resulting
from the defect . . . [and] identify the location of each alleged construction
defect sufficiently to enable the responding parties to locate the alleged
defect without undue burden.”[100]
Claimants must “endeavor” to serve notice within fifteen (15) days after
discovery of an alleged defect, although untimely service of notice will not
bar the filing of an action.[101]
A person served with a Chapter 558 Notice “is entitled to perform a reasonable
inspection of the property or of each unit subject to the claim to assess each
alleged construction defect” within thirty (30) days after service of the
notice, or within fifty (50) days for claims involving more than twenty (20)
parcels.[102]
Subject to conditions within the Chapter, if the person
served with notice of a claim concludes destructive testing is necessary to
determine the nature and cause of each alleged construction defect, these
inspections may even include destructive testing under certain terms and
conditions set forth in the statute.[103]
Within forty-five (45) days after service of a notice, or within seventy-five
(75) days after service of a notice involving more than 20 parcels, the
recipient must serve a written response to the claimant.[104]
The response must be in the nature of one of the following: (a) an offer to
remedy the alleged construction defect at no cost to the claimant with a
detailed description of the proposed repairs and a timetable for completion;
(b) an offer to settle the claim by monetary payment that will not obligate the
person’s insurer, with a timetable for making the payment; (c) an offer to
settle the claim with a combination of repairs and monetary payment that will
not obligate the person’s insurer, that includes a detailed description of the
proposed repairs and a timetable for completion of repairs and making payment;
(d) a statement that the person disputes the claim and will not remedy the
defect or settle the claim; or (e) a statement that a monetary payment,
including insurance proceeds, if any, will be determined by the person’s
insurer within thirty (30) days after notification to the insurer of the claim.[105]
Within ten (10) days of receipt of a notice of claim, or
within thirty (30) days for claims involving more than twenty (20) parcels, the
party served with a notice may also serve a copy of the notice to each
contractor, subcontractor, supplier, or design professional whom it reasonably
believes is responsible for each defect specified in the notice of claim,
noting the specific defect for which it believes each party served is
responsible.[106]
Parties receiving notices in this manner may inspect the property in the same
manner as provided for as to the original recipient.[107]
Within fifteen (15) days after service of a notice in this manner, or within
thirty (30) days for claims involving more than twenty (20) parcels, the person
served must serve a written response to the person from which he or she
received the notice.[108]
The response must include a report, if any, of the scope of any inspection
performed of the property and the findings and results of the inspection.[109]
The response may also include one or more offers or statements as provided for
as to the original recipient’s response.[110]
Upon request, the claimant and any person served with
notice under the Chapter, shall exchange any “design plans, specifications, and
as-built plans; photographs and videos of the alleged construction defect
identified in the notice of claim; expert reports that describe any defect upon
which the claim is made; subcontracts; purchase orders for the work that is
claimed defective or any part of such materials; and maintenance records and
other documents related to the discovery, investigation, causation, and extent
of the alleged defect identified in the notice of claim and any resulting
damages.”[111]
Expert reports exchanged between the parties during the pre-suit process may
not be used in any subsequent litigation for any purpose, with the exception of
a testifying expert, and a party may assert any claim of privilege recognized
under Florida law in response to a document request.[112]
Any party who fails to provide requested materials is subject to the same
sanctions as a court may impose for a discovery violation.[113]
If the person served with a claim disputes the claim and
will not agree to either remedy the defect or settle the claim, or does not
respond to the notice within the time provided, a claimant may proceed with an
action without further notice.[114] A claimant who receives a timely settlement
offer must accept or reject the offer by serving written notice on the person
making the offer within forty-five (45) days after receipt.[115]
The service of a written Chapter 558 Notice tolls the
applicable statute of limitations related to any person covered under the
Chapter until the later of either ninety (90), or one-hundred-twenty (120),
days, as applicable, after service of the notice or thirty (30) days after the
end of the repair or payment period stated in an offer.[116] While not expressly stated in the Chapter and
presently controverted, at least one Florida jurisdiction recognizes that a
pre-suit Chapter 558 notice can be used to negate the statute of repose.[117]
Providing of a copy of a Chapter 558 notice to an insurer,
if applicable, does not constitute a claim for insurance purposes unless the
terms of the policy specify otherwise.[118]
However, the Florida Supreme Court more recently analyzed the Chapter 558
pre-suit processing in the context of determining whether the process is a
“suit” for the purposes of analyzing whether service and receipt of a notice
under the Chapter triggers an insurer’s duty to defend and indemnify an
insured.[119]
The policy at issue before the Florida Supreme Court broadened the definition
of a “suit” beyond more than just civil proceedings alleging damages to which
the policy applied; under the policy, a “suit” included “[a]ny other
alternative dispute resolution proceeding in which such damages are claimed and
to which the insured submits with our consent.”[120]
Tracking this policy language, the Florida Supreme Court found that under the
terms of the policy, if the insurer consents to submission of defect claims to
the Chapter 558 process, the process is a “suit” as defined under the policy
and invokes the insurer’s duty to defend.[121]
The Court, however, did not address whether the insurer in question did or did
not consent to its insured’s participation in the Chapter 558 process, and
therefore whether the process was, in the context of this case, actually a
“suit,” or not.[122]
V.
Insurance Coverage and Allocation Issues
A.
General Coverage Issues
“Coverage” in the insurance context encompasses two duties
an insurance company has with respect to its insured: the duty to defend and
the duty to indemnify.[123] The duty to defend is distinct from and
broader than the duty to indemnify.[124] An
insurer’s obligation to defend a claim made against its insured is determined
from the allegations in the complaint and the applicable language of the
policy. All doubts concerning the duty
to defend are resolved in favor of providing a defense.[125]
Accordingly, if the allegations set forth any facts potentially bringing a
claim within the scope of coverage, the insurer has a duty to defend; “and if
the complaint alleges facts showing two or more grounds for liability, one
being within the insurance coverage and the other not, the insurer is obligated
to defend the entire suit.”[126]
“Consequently, an insurer may be required to defend a suit even if the true
facts later show that there is no coverage.”[127]
The duty to indemnify, however, is much narrower than the
duty to defend. “In contrast to the duty to defend, the duty to indemnify is
dependent upon the entry of a final judgment, settlement, or a final resolution
of the underlying claims by some other means.”[128]
Therefore, while the duty to defend is measured by allegations, even if the
facts alleged are untrue or legal theories are ultimately unsound, “the duty to
indemnify is measured by the facts as they unfold at trial or are inherent in
the settlement agreement.”[129]
Under Florida law, insurance contracts are construed in
accordance with the plain language of the policy as bargained for by the
parties, giving each term its plain and unambiguous meaning.[130]
The language and terms of an insurance contract likewise determine the scope
and extent of insurance coverage afforded.[131]
Insuring clauses in policies “are construed in the broadest possible manner to
affect the greatest extent of coverage.”[132]
Any “ambiguities are interpreted liberally in favor of the insured and strictly
against the insurer who prepared the policy.”[133]
A party seeking coverage under an insurance policy has the
initial burden of proving that the underlying claim against is within the
coverage of the policy.[134] Only
once coverage is established does the burden shift to the insurer to establish
the applicability of any exclusions.[135] However,
the burden does rest on the insurer to show that exclusions in a policy apply.[136]
B.
Trigger of Coverage
Commercial general liability (“CGL”) policies are most
often purchased on an occurrence coverage basis. This generally means insurance coverage is
afforded under CGL policies for “personal injury,” “property damage,” etc.,
caused by an “occurrence” and which occurs during the policy period. An
“occurrence” is generally defined as an accident including continuous or
repeated exposure to substantially the same general harmful conditions.
Therefore, coverage is triggered when an “occurrence” results in “personal
injury” or “property damage;” however, this inquiry becomes more complicated
when multiple policies, causes, and damages are involved.
To trigger coverage under a specific policy, Florida law
generally recognizes that while the damage itself must occur during a policy
period, the “occurrence” need not.[137]
In determining at what time damage occurs, Florida recognizes four, generally
accepted “trigger of coverage” theories: (1) exposure; (2) manifestation; (3)
continuous trigger; and (4) injury in fact.[138]
Under the exposure theory, property damage occurs upon installation of the
defective product.[139]
Under the manifestation theory, property damage occurs at the time the damage
manifests itself or is discovered.[140]
The continuous trigger theory defines property damage as occurring continuously
from the time of installation until the time of discovery.[141]
Finally, under the injury-in-fact trigger, sometimes referred to as
damage-in-fact, in the context of property damage, coverage is triggered when
the property damage underlying the claim actually occurs.[142]
Usually, discussions of exposure and continuous trigger theories are confined
to asbestos and toxic-tort cases, respectively.
Florida courts have adopted both the manifestation and
injury-in-fact triggers.[143] The disagreement stems from differing
interpretations of two cases – Trizec Properties, Inc. v. Biltmore
Construction Co., 767 F.2d 810 (11th Cir.1985), and Travelers Insurance
Co. v. C.J. Gayfer’s & Co., 366 So. 2d 1199 (Fla. 1st DCA 1979).[144]
In Gayfer’s, the court interpreted the term
“occurrence” in a policy provision that read as follows: “[The Insurer] will
pay on behalf of the Insured all sums which the Insured shall become legally
obligated to pay as damages because of bodily injury or property damage . . .
caused by an occurrence” during the policy period.[145]
The underlying suit alleged that the insured negligently installed a roof
drainage system during the policy period, and, after the policy period expired,
a joint in the drainage system failed, discharging water into the building.[146]
The Gayfer’s court never discussed when the damage occurred because it
was undisputed that the damages occurred after the policy expired.[147]
Rather, the Gayfer’s court was concerned with whether the fact that a negligent
act that caused the damage occurred during the policy period was enough to
trigger coverage, or if the actual damage had to have occurred during the
policy period.[148]
To resolve this issue, the court looked at the definition
of “property damage” from the policy, which stated that “property damage means
the physical injury to or destruction of tangible property which occurs during
the policy period including the loss of use thereof at any time resulting
therefrom, or . . . loss of use of tangible property which has not been
physically injured or destroyed provided such loss of use is caused by an
occurrence during the policy period.”[149]
The court determined that the language of the policy was unambiguous and that
the damage itself—not just the negligent act—had to occur during the policy
period.[150]
In explaining its holding, the court stated that “[t]he term ‘occurrence’ is
commonly understood to mean the event in which negligence manifests itself in
property damage or bodily injury, and it is used in that sense here.”[151]
Following this ruling, two decisions interpreted the
sentence in Gayfer’s mentioning the word “manifests” to mean that
Florida now followed the manifestation trigger theory.[152]
Several subsequent cases have continued to follow those decisions’ lead without
separately analyzing Gayfer’s; which, as noted, only addressed the issue
of whether a negligent act alone was sufficient to trigger coverage, not when
damage “occurs” to trigger coverage.[153]
However, in a subsequent decision, the Eleventh Circuit in Trizec,
unlike the court in Gayfer’s, did address the issue of when damage
occurs in order to trigger coverage.[154]
In Trizec, a roof deck was negligently installed, causing water intrusion
damage.[155]
The policy at issue in Trizec applied to “property damage . . . caused
by an occurrence,” and property damage was defined in part as “physical injury
to or destruction of tangible property occurring during the policy period.”[156]
The Trizec court therefore interpreted this language as requiring an
injury-in-fact analysis, stating that “the damage itself . . . must occur
during the policy period for coverage to be effective” and that “[t]here is no
requirement that the damages ‘manifest’ themselves during the policy period” in
order to trigger coverage.[157]
After determining an occurrence appropriately falls within
policy coverage, the next piece of the trigger puzzle is an analysis of whether
the occurrence is the “cause” of the injury or damages. Sometimes more than one
factor or a combination of circumstances give rise to a party’s loss or
damages. In this scenario, Florida follows two standards for determining
whether a claim is covered when damage is the result of more than one cause:
the concurrent cause doctrine and the efficient proximate cause doctrine.[158]
Which standard applies depends on whether the causes are dependent or
independent from each other.[159]
“Causes are independent when they are unrelated such as an earthquake and a
lightning strike, or a windstorm and wood rot.”[160] “Causes
are dependent when one peril instigates or sets in motion the other, such as an
earthquake which breaks a gas main that starts a fire.”[161]
If causes are independent of each other, then the
concurrent cause doctrine applies.[162]
Under the concurrent cause doctrine, coverage is provided so long as one cause
is covered, even if other causes are not covered.[163]
Dependent causes are analyzed under the efficient proximate
cause doctrine, where the “efficient proximate cause” is the cause that
instigates or sets the others in motion.[164]
A loss caused by multiple perils will be covered if the “efficient proximate
cause” is a covered peril; if the “efficient proximate cause” is not covered
under the policy, then the claim for damages is not covered even if the other
causes are covered. However, the efficient proximate cause doctrine will not be
incorporated into an insurance policy, if doing so renders part of the policy
meaningless.[165]
For example, where the efficient cause of damage is a “necessary antecedent of
the damages’ direct cause,” the efficient proximate cause doctrine will not be
applied.[166]
In Arawalk, the Eleventh Circuit was called upon to
determine whether the efficient proximate cause doctrine should be applied to
analyzing coverage for damages to a plane’s engine caused by overheating.[167]
Overheating was excluded under the policy as “wear and tear;” but plaintiff’s
negligence allegedly caused the overheating, and negligence was covered by the
policy.[168]
Recognizing that negligence, the covered cause, is almost always the efficient
cause of “wear and tear,” the Eleventh Circuit, applying Florida law, held that
the loss was not covered because any wear and tear exclusion could effectively
be eviscerated if the insured could show that up-keep was not properly
performed.[169]
Among all of the other hotly-contested trigger-of-coverage
issues is the scope of loss, damages, or injury; namely, what property damages
or construction defects are covered under comprehensive general liability
policies. In 2007, the Florida Supreme Court in U.S. Fire Insurance Co. v.
J.S.U.B., Inc., analyzed “whether a post-1986 standard form commercial
general liability (CGL) policy with products-completed operations hazard
coverage, issued to a general contractor, provides coverage when a claim is
made against the contractor for damage to the completed project caused by a
subcontractor’s defective work.”[170]
Several prior opinions had established that from a policy
perspective, the purpose of CGL coverage is to provide protection for personal
injury or for property damage caused by the completed product, but not for the
replacement and repair of that product.[171]
Previous precedent based upon both this policy consensus and exclusionary language
contained in pre-1986 CGL policies consistently held that faulty workmanship
that damages the contractor’s own work can never constitute a covered
“occurrence.”[172]
The Florida Supreme Court addressed this well-recognized proposition of Florida
law head on, noting none of the previous opinions expressly considered whether
it was appropriate to apply this rationale to cases involving different policy
provisions.[173]
Further, because the leading case on this point involved a claim of faulty
workmanship by a contractor, rather than a claim of faulty workmanship by a
subcontractor, the court determined it should not be binding and looked to the
language of the post-1986 CGL policy it was faced with as its primary guidance
in resolving the dispute.[174]
In doing so, the court first addressed “whether a
subcontractor’s faulty workmanship that results in damage to the contractor’s
work can constitute an ‘occurrence’ as that term has been defined under Florida
case law.”[175]
After parsing the differences between a contractor’s work and a subcontractor’s
work including the differing end products, the court concluded “that faulty
workmanship that is neither intended nor expected from the standpoint of the
contractor can constitute an ‘accident’ and, thus, an ‘occurrence’ under a
post-1986 CGL policy.”[176]
Next, the court turned to an analysis of what constitutes “property damage,”
recognizing that in order to determine whether a policy provides coverage for
an insured’s losses, it must address whether the “occurrence” caused “property
damage” within the meaning of the policies.[177]
Starting with the premise “that there is a difference
between a claim for the costs of repairing or removing defective work, which is
not a claim for ‘property damage,’ and a claim for the costs of repairing
damage caused by the defective work, which is a claim for ‘property damage,’”
the court found that the claims alleged in the case before it did not involve a
claim for the cost of repairing the subcontractor’s defective work, but rather
a claim for repairing the structural damage to the completed homes caused by
the subcontractor’s defective work.[178]
Noting that the cause of the claimed structural damage in the case before it
was “physical injury to tangible property,” the court concluded that the structural
damage to the homes was in fact “property damage” within the meaning of the
policy.[179]
Therefore, the court held, “physical injury to the completed project that
occurs as a result of the defective work can constitute ‘property damage’ as
defined in a CGL policy.”[180]
Accordingly, “a post–1986 standard form commercial general liability policy
with products completed-operations hazard coverage, issued to a general
contractor, provides coverage for a claim made against the contractor for
damage to the completed project caused by a subcontractor’s defective work
provided that there is no specific exclusion that otherwise excludes coverage.”[181]
The Florida Supreme Court further interpreted and applied
the J.S.U.B. ruling in its subsequent decision in Auto-Owners
Insurance Company v. Pozzi Window Company.[182]
There, the facts involved claims that water intrusion was occurring due to
either defective windows or defective installation of windows. However, the
court could not determine the ultimate outcome in the case because it did not
have a sufficient factual basis to apply the legal principles that it
established. The court ruled instead that “if the claim in this case is for the
repair or replacement of windows that were defective both prior to installation
and as installed, then that is merely a claim to replace a ‘defective
component’ in the project”[183]
and it is not covered because there would be no “property damage” under the
policies. In contrast, “if the claim is for repair or replacement of windows
that were not initially defective but were damaged by the defective
installation, then there is physical injury to tangible property” and the claim
is covered.[184]
C.
Allocation Among Insurers
Allocation among insurers is ordinarily determined by
applying the explicit terms of the relevant insurance policies. Florida “courts
will not rewrite insurance policies, nor add meaning that is not present, or
otherwise reach results contrary to the intentions of the parties.”[185]
Moreover, “Where two or more policies of insurance each contain similar ‘other
insurance’ clauses whereby the insurers attempt to limit their liability for an
insured’s loss covered by these policies, proration according to the policy
limit is the proper method of determining the liability of the respective
insurers.”[186]
In considering whether the coverage provided by insurance policies is primary
or excess under Florida law, courts determine the intent of the parties “solely
by the language of the policies unless the language is ambiguous.”[187]
Therefore, when “there is no incompatibility among other insurance provisions,
they are to be enforced by their terms.”[188]
In Florida, there are three basic types of “other
insurance” clauses: escape, excess, and pro rata.[189]
An escape clause completely voids the insurance coverage and includes language
such as “this insurance shall not apply” or is “void” if other collectible
insurance applies.[190]
An excess clause does not void the coverage but merely provides that the
coverage will be “excess” over other valid and collectible insurance.[191]
Finally, a pro-rata clause provides that each insurer will be
responsible for a share of total liability on a pro-rated basis.[192]
Under Florida law, when other insurance clauses are
“mutually repugnant,” the coverage is deemed to be pro rata.[193]
The reported decisions are not entirely consistent on what constitutes mutual
repugnancy, referring variously to “other insurance” clauses. The challenge in
these circumstances becomes the determination of when such provisions are in
fact “repugnant.”
On June 18, 2019, Florida Governor Ron DeSantis signed into
law House Bill 301, which creates section 624.1055, Florida Statutes. The
statute creates a right of contribution among liability insurers for defense
costs whenever an insurer has a duty to defend claims or suits filed in the State
of Florida. Prior to the passage of House Bill 301, under Florida law, there
was no right to contribution among primary co-carriers.[194]
In Argonaut, the Third District Court of Appeal found that “the duty of
each insurer to defend its insured is personal and does not insure to the
benefit of another insurer.”[195]
However, since the enactment of section 624.1055, insurers who have paid more
than their “fair share” of defense costs will have an independent right to seek
contribution against co-carriers who share that duty.[196]
To state a claim for equitable contribution, “insurers must “share (1) the same
level of obligation (2) on the same risk (3) to the same insured.”[197]
The statute applies to contribution claims related to the defense of insureds
and additional insureds, as the statute states that it applies to any claim,
suit, or other action initiated on or after January 1, 2020.
D.
Issues with Additional Insurance
In 2003, the legislature enacted Chapter 558, Florida
Statutes, to provide “an alternative method to resolve construction disputes”
between owners and contractors. The Chapter 558 process begins when an owner or
claimant serves a written Chapter 558 notice on a contractor (or subcontractor,
supplier, or design professional). The current version of the statute requires
that a claimant serve a written notice of claim describing “in reasonable
detail the nature of each alleged construction defect and, if known, the damage
or loss resulting from the defect. Based upon at least a visual inspection by
the claimant or its agents, the notice of claim must identify the location of
each alleged construction defect sufficiently to enable the responding parties
to locate the alleged defect without undue burden. The claimant has no
obligation to perform destructive or other testing for purposes of this
notice.”[198]
The Florida Supreme Court discussed the Chapter 558 process
in its seminal decision in Altman Contractors, Inc. v Crum & Forster
Specialty Ins. Co.[199]
The Florida Supreme Court’s decision arose out of a declaratory judgment
action filed by Altman Contractors, Inc. (“Altman”) in the U.S. District Court
for the Southern District of Florida. Altman is based upon construction defect
claims brought by the Sapphire Fort Lauderdale Condominium Association, Inc. (the
“Association) against Altman, wherein the Association served Altman with several
Chapter 558 notices of claim regarding a multitude of defects to the
condominium. Altman notified its insurance carrier, Crum & Forrester
(“Crum”) and demanded that Crum defend and indemnify Altman against the
Association’s claims. Crum denied that it had any to duty to defend Altman on
the basis that the claim was not in suit; however, Crum exercised its
discretion to retain counsel to defend Altman against the Association’s claims
subject to a reservation of rights. Altman objected to Crum’s denial of coverage
and rejected the counsel selected by Crum. Altman demanded that Crum pay for
its defense costs incurred after being served by the Association with the
Chapter 558 Notice. After Crum denied Altman’s demands, Altman settled its
claims with the Association and filed its declaratory judgment action seeking a
declaration that Crum owed Altman a duty to defend and indemnify Altman under
its policies, as well as reimbursement for its fees and costs.
Ultimately, the U.S. District Court ruled in favor of Crum
finding that the Association’s Chapter 558 notices did not constitute a “suit”
under the CGL policies.[200]
Altman appealed the action to the U.S. Court of Appeals for the 11th Circuit,
which later certified the following question to the Florida Supreme Court: “Is
the notice and repair process set forth in Ch. 558, Florida Statutes, a ‘suit’
within the meaning of the commercial general liability policy issued by [Crum]
to [Altman]?”
The Florida Supreme Court ultimately held in Altman
that “[a]lthough the chapter 558 process does not constitute a ‘civil
proceeding,’ it is included in the policy’s definition of ‘suit’ as an
‘alternative dispute resolution proceeding’ to which the insurer’s consent is
required to invoke the insurer’s duty to defend the insured.”[201]
As a result of the Florida Supreme Court’s decision in Altman, general
contractors have attempted to circumvent Altman by pleading generally in
their declaratory judgment complaints that insurers have “consented” to
participation in the chapter 558 process, or alternatively, have waived
consent. Whether these allegation pass muster, is presently up for debate.
VI.
Contractual Indemnification
A contract for
indemnity is an agreement by which the promisor agrees to protect the promisee
against loss or damages because of liability to a third party. The right to
indemnity arises through either an express or implied contract; and are
accordingly subject to the general rules governing formation, validity, and
construction of all contracts.
Well-settled
Florida law disfavors, and generally invalidates, exculpatory agreements that
seek to shift “the cost of a party’s misconduct from the perpetrator to the
injured party ‘because they relieve one party of the obligation to use due care
and shift the risk of injury to the party who is probably least equipped to
take the necessary precautions to avoid injury and bear the risk of loss.’”[202] Because indemnification agreements can
potentially produce the same result as an exculpatory provision by shifting
responsibility for the payment of damages back to the injured party, they are
strictly construed and scrutinized by the courts.[203]
An agreement for
indemnification that protects an indemnitee against its own negligence is valid[204] as long as the contract expresses in clear
and unequivocal terms an intent to indemnify against the indemnitee’s own
wrongful actions.[205] Thus, contracts purporting to indemnify a
party against its own negligence will be enforced only if they clearly express
such an intent. A general provision indemnifying the indemnitee against any and
all claims, standing alone, is not sufficient.[206] In addition, if a contractual indemnity
provision requires reference to other parts of the contract to ascertain its
meaning, then it does not contain the clear and unequivocal terms required to
indemnify the indemnitee against its own negligence.[207]
The question of
construction of an indemnity contract is usually one of law for the court
applying recognized rules of construction.[208] Thus, the terms of the indemnity contract
determine whether the indemnitor is obligated to reimburse the indemnitee for a
particular claim.[209] The contract must be construed according to
the intention of the parties as gathered from the writing and the circumstances
under which the writing was made in the particular case.[210] Accordingly, the intent of the parties and
the scope of the indemnification provision are derived from the language of the
contract and the circumstances in which it was made.[211]
Notwithstanding
these general rules, any portion of an agreement or contract for construction,
alteration, repair or demolition of a building or structure is void and unenforceable
under Florida law where a party to the contract seeks to obtain indemnification
from another party for its own active negligence,[212] unless the contract contains a monetary
limitation on the extent of the indemnification that bears a reasonable commercial
relationship to the contract and is part of the project specifications or bid
documents, if any.[213] An indemnification provision subject to this
requirement may not require that the indemnitor indemnify the indemnitee for
damages to persons or property caused in whole or in part by any act, omission,
or default of a party other than: “(a) the indemnitor; (b) any of the
indemnitor’s contractors, subcontractors, sub-subcontractors, materialmen, or
agents of any tier or their respective employees; or (c) the indemnitee or its
officers, directors, agents, or employees.”[214]
However, an
explicit exception exists if a design professional provides professional
services for a public agency, that agency may require a professional services
contract under which the professional indemnifies and holds harmless the
agency, and its officers and employees from liabilities, damages, losses, and
costs, including but not limited to, reasonable attorneys’ fees, to the extent
the injury was caused by the negligence, recklessness, or intentionally
wrongful conduct of the design professional and other persons employed or
utilized by the design professional in the performance of the contract.[215]
Where the liability
of the obligor under a contract is not based on an indemnity clause but on the
obligor’s breach of contract by failing to make the obligee a named insured as
required by the contract, such action is distinguishable from the case where
the contract requires the indemnitee to be insured by a policy of insurance maintained
by the indemnitor.[216]
VII.
Contingent Payment Agreements
A.
Enforceability
A contract may have
conditions required to be performed prior to the payment obligation becoming
due. The most common contingency to payment is that a contractor receive
payment from an owner. However, there may be other contingencies to payment,
such as the furnishing of a satisfactory release.[217] In these cases, where the parties agreed to
such terms, absent any applicable contract formation defenses, a party failing
to show it furnished a satisfactory release cannot prove its case as failure to
furnish a satisfactory release under the contract is a failure to perform a
condition precedent to payment.
B.
Requirements
In order for a
“pay-when-paid” provision to be enforceable, the terms of the subcontract must
clearly and unambiguously explain that the subcontractor fully accepts the risk
that the owner may not pay the general contractor, and in that instance, the
subcontractor will not be paid for its work until the general contractor has
been paid.[218] Unless the terms of the subcontract are
clear and unambiguous and the intention to transfer risk to the subcontractor
is obvious, the “pay-when-paid” provision is likely not enforceable.
Where it is clear
and unambiguous from the contract that payment to the subcontractor is not
earned and is not payable at all unless payment for the subcontractor’s work is
received by the contractor from the owner, then such a clause is enforceable.[219]
The courts have
provided insight as to what interpret as “clear and unambiguous terms.” For
instance, the Florida Supreme Court found a clause that stated that final
payment would be made to a subcontractor “within 30 days after the completion
of the work included in this subcontract, written acceptance by the architect and
full payment therefore by the owner” to be ambiguous and unenforceable.[220] Likewise, a District Court of Appeals found
a “pay when paid” clause that stated “Payments will be made for the value of
the work installed each week within seven (7) business days after receipt of
payment from the owner” to be ambiguous and unenforceable.[221]
VIII.
Scope
of Damage Recovery
A.
Personal
Injury Damages vs. Construction Defect Damages[222]
In a construction defect case, the
recoverable damages are generally the reasonable cost of construction and
completion under the terms of the contract, unless such an award would be
unreasonable or constitute economic waste.[223]
Where the award would be unreasonable or constitute economic waste, damages
will be calculated by the value that the product contracted for would have held
if properly constructed, less the value of the product that was actually
delivered.[224]
In contrast, personal injury plaintiffs who
have proven liability are entitled to recover an amount that will fairly and
adequately compensate them for their injuries. This amount may be derived from
numerous factors including compensation for injury, pain, emotional distress,
disability, disfigurement, loss of capacity for enjoyment of life, past and
future medical expenses, lost past earnings, and lost earning capacity.[225]
Additionally, the spouse of a plaintiff can
recover for loss of consortium and services.[226]
Parents of a plaintiff can recover damages for their care and treatment of
their minor child, loss of their child’s services, earnings, and earning
capacity, and loss of filial consortium for the period of the child’s minority.[227]
B. Attorney’s Fees Shifting and Limitations on
Recovery
Florida follows the “American Rule” with
respect to entitlement to attorneys’ fees, providing that “attorney’s fees
incurred while prosecuting or defending a claim are not recoverable in the
absence of a statute or contractual agreement authorizing their recovery.”[228] Further, entitlement for attorneys’ fees,
whether based on contract or statute, must be pled.[229]
One inherent premise of the “American Rule”
is that an award of attorneys’ fees is, foremost, in derogation of common law.[230] Therefore, attorneys’ fees are unavailable
in common-law actions unless a distinct statutory or contractual authority
authorizing recovery of fees exists.[231]
While prevailing-party fee clauses are common
and enforceable under Florida law, a contractual attorneys’ fee provision must
be strictly construed.[232] A typical prevailing-party clause is set
forth using standard language similar to the following: “The prevailing party in litigation arising
from this contract shall be entitled to recover attorneys’ fees and costs from
the nonprevailing party.”[233] Florida law statutorily requires any
contractual fee provision to operate reciprocally; section 57.105(7), Florida
Statutes, provides that “[i]f a contract contains a provision allowing
attorney’s fees to a party when he or she is required to take any action to enforce
the contract, the court may also allow reasonable attorneys’ fees to the other
party when that party prevails in any action.[234]
Fees provisions in the construction industry
become complicated, especially with the prevailing use of indemnification provisions.
It is important to understand which type of provision a contract contains or
which to rely upon in each circumstance. As a general rule, “‘an indemnitee is
entitled to recover, as part of his damages, reasonable attorney’s fees and
reasonable and proper legal costs and expenses, which he is compelled to pay as
a result of suits by or against him in reference to the matter against which he
is indemnified.’”[235] However, indemnification clauses that do not
limit recovery of attorneys’ fees to the prevailing party in suits between the
parties to the indemnification contract are construed under Florida law to
apply only to claims by third parties.[236] The distinction between recovery of fees
incurred in defending against third-party claims versus fees incurred in
prosecution of first-party claims arises from arguably the most basic of
Florida’s contract jurisprudence.
Well-settled Florida law disfavors, and
generally invalidates, exculpatory agreements that seek to shift “the cost of a
party’s misconduct from the perpetrator to the injured party ‘because they
relieve one party of the obligation to use due care and shift the risk of
injury to the party who is probably least equipped to take the necessary
precautions to avoid injury and bear the risk of loss.’”[237] Because indemnification agreements can
potentially produce the same result as an exculpatory provision by shifting
responsibility for the payment of damages back to the injured party, they are
strictly construed and scrutinized by the courts.[238] Indeed, “the view that general indemnity
language automatically includes indemnity for first-party claims would ‘permit
a garden variety indemnity clause to be used to exculpate a contracting party
from liability to the other party to the agreement.’”[239]
For these reasons, Florida courts have
continually recognized that indemnity provisions which do not limit recovery of
attorneys’ fees to the prevailing party apply only to fees incurred for claims
brought by third parties and are not applicable for fees incurred to defend or
prosecute claims between the parties to the indemnification contract.[240]
Therefore, for indemnity for attorneys’ fees
to apply in first-party claims, the provision must clearly and unambiguously
show an intent to extend indemnity to first-party claims between the parties to
the contract; and “[a]n indemnity provision that is silent or unclear whether
it applies to first-party claims will normally be interpreted to apply only to
third-party claims.”[241]
Florida’s Fourth District in Century Village v. Chatham Condominium
Associations, was one of the first Florida court to address application of
an indemnification clause in this context to actions between the contracting
parties.[242] The applicable indemnification clause in the
case before the Fourth District provided as follows:
INDEMNIFICATION
Lessee covenants and agrees with Lessor that
during the entire term of this Lease, the Lessee will indemnify and save
harmless the Lessor against any and all claims, debts, demands, or obligations
which may be made against Lessor, or against Lessor’s title of the premises,
arising by reason of or in connection with the making of this Lease and the
ownership by Lessee of the interest created in the Lessee hereby, and if it
becomes necessary for the Lessor to defend any action seeking to impose such
liability, the Lessee will pay the Lessor all costs of Court and attorney’s
fees incurred by the Lessor in effecting such defense, in addition to any other
sums which the Lessor may be called upon to pay by reason of the entry of a
judgment against the Lessor in the litigation in which such claim is asserted.[243]
Finding it was “quite obvious” that the
clause was not intended to apply to actions between the parties, but that it
was rather intended to apply to third-party actions, the court held that the
Lessor was not entitled to recover attorneys’ fees incurred in defending a suit
by the Lessee.[244] The court specifically cautioned that
finding otherwise “would amount to accepting the incongruous theory that
although the [Lessees] may be successful in their litigation, they would
nevertheless have to satisfy their own judgment in addition to paying the
lessor’s costs.”[245]
Following this ruling, the Florida Supreme
Court adopted the Third District’s reasoning in analyzing a similar indemnity
provision in Penthouse North Association
v. Lombardi, 461 So. 2d 1350 (Fla. 1985). In Penthouse, a condominium association filed an action against its
directors, which the trial court dismissed after finding the action was barred
by the statute of limitations.[246] Following dismissal, the trial court found
the association’s articles of incorporation did not authorize an award of
attorneys’ fees for the prevailing party in the case at hand and struck the
directors’ request for attorneys’ fees.[247] Explicitly adopting the Century Village reasoning on appeal, the supreme court found that a
theory recognizing indemnification between the parties to the contract would
produce an incongruous result and held that no statutory or contractual basis
for an award of attorneys’ fees existed between the parties below.[248]
In Sunshine
Bottling Co. v. Tropicana Products, Inc., the Third District again analyzed
a claim for attorneys’ fees in the context of a first-party dispute rising out of
a contract between Tropicana and its orange juice bottler, Sunshine.[249] Sunshine filed suit against Tropicana for
breach of contract and promissory estoppel following a dispute that arose when
Tropicana altered its canning specifications.[250] Tropicana counterclaimed for promissory
estoppel, quantum meruit, and breach of contract, and requesting
recovery of attorneys’ fees.[251] A jury found in favor of Sunshine on all
claims and awarded Sunshine $592,000 for damages on its promissory estoppel
claim.[252] Following post-trial motions, on appeal, the
Third District in reviewing the parties’ contract, noted although the contract
at issue contained an indemnification clause whereby the parties “agreed to
indemnify each other for damages and other losses (including fees) arising from
litigation brought by third parties for injuries or damages attributable to the
party not sued[,]” the contract did not contain a prevailing-party, fee
shifting provision in the event of litigation between the parties.[253] Recognizing that in the absence of a clear
and unambiguous contractual provision or a statutory right, each party is
responsible for its own attorneys’ fees, the court held that Sunshine had no
contractual or statutory basis for recovery of its attorneys’ fees incurred in
prosecuting or defending the first-party claims between the contracting parties
and was not entitled to fees in the action below.[254]
The First District Court of Appeals similarly
denied recovery of attorneys’ fees to a prevailing party in a breach of
contract action in Traylor Bros. v.
Melvin, 776 So. 2d 947, 948 (Fla. 1st DCA 2000). Citing the Penthouse holding, in its short,
succinct opinion, the First District noted despite prevailing on its contract
action, the contract at issue below contained indemnification clauses, which
“do not provide for an award of attorney’s fees to the prevailing party in
litigation between the contracting parties.”[255]
Aside from a contractual agreement, some of
the more commonly encountered statutory provisions providing for recovery of
attorneys’ fees are Florida’s “frivolous lawsuit” statute, section 57.105, and
Florida’s “Offer of Judgment and Demand for Judgment” statute, section 768.79.[256]
Section 57.105(1)(a), Florida Statutes,
requires a court to award the prevailing party reasonable attorneys’ fees, in
equal amounts by the losing party and the losing party’s attorney, on any claim
or defense at any time during a civil proceeding or action in which the court
finds that the losing party or the losing party’s attorney knew or should have
known that a claim or defense when initially presented to the court or at any
time before trial was not supported by the material facts necessary or would
not be supported by the application of then-existing law to those material
facts.[257] “The word ‘shall’ in section 57.105 has been
found to evidence the legislative intent to impose a mandatory penalty in the
form of reasonable attorney’s fees to discourage baseless claims, by placing a
price tag on losing parties who engage in these activities.”[258] Counsel for a party may also be held liable
for attorney’s fees under section 57.105 if counsel failed to conduct an
objective, reasonable investigation of material facts supporting his client’s
claim.[259]
Florida’s “Offer of Judgment and Demand for
Judgment” statute serves as an enticement to settle claims by imposing
sanctions in the form of fees and costs upon a party who unreasonably rejects a
settlement offer made pursuant to the statute.[260] Pursuant to the statute, a party who rejects
an offer and does not do at least seventy-five (75) percent as well as offered
at trial, i.e., the opposing party beats his or her offer at trial by at least
twenty-five (25) percent, the party rejecting the offer will have to pay the
offeror’s attorneys’ fees and costs from the date of the offer.
C. Consequential Damages
A party may recover consequential damages,
subject to the traditional limitations related to causation, foreseeability,
and certainty.[261] The party seeking consequential damages must
specifically include a reference to the same factors in their complaint.[262]
D. Delay and Disruption Damages
In Florida, a party is entitled to recover
losses that accrued as a result of a delay or disruption in construction or
improvement of the subject property.[263] These damages are strictly governed by
statute and case law.
A compensable delay is one caused by the
party receiving the work, that impacts the critical path of the contractor, and
results in extra cost to the contractor, which are not concurrent with the
contractor’s delay.[264] To find that the party receiving the work
caused compensable delay in performance of a contract, the general rule is that
someone other than the contractor, or one for whom the contractor is
responsible, must have been the sole proximate cause of the contractor’s
additional loss, and the contractor would not have been delayed for any other
reason during that period.[265]
Excusable delays may also be defined in the
contract. A breach of common-law duties of good faith and fair dealing may also
be the basis for claims of compensable delay and disruption, entitling the
contractor to an equitable adjustment.[266]
Nevertheless, a contract may include a
“no-damage-for-delay” clause, which may be enforceable if the clause is clearly
worded.[267] Of particular note, since a
no-damage-for-delay clause may relieve a party from the consequences of his or
her own actions they are strictly construed.
E. Economic Loss Doctrine
The Florida Supreme Court’s decision in Tiara Condominium Association v. Marsh &
McLennan Companies, in 2013, was widely regarded as a significant retreat
in the scope of the economic loss rule.[268] Historically, the rule bars an action in
tort for claims arising in products liability where the plaintiff has suffered
no personal injury or damage to other property.[269] Initially, the economic loss rule served to
offer manufacturers protection from liability for economic damages caused by a
defective product by limiting liability to the damages provided by warranty
law.[270] With the introduction of strict liability
for personal injury cases, courts began to hear cases questioning whether they
should permit causes of action in tort for purely economic damages caused by
defective products.[271] The strict liability doctrine was not
intended to undermine the warranty provisions of contract law, but rather to
govern the separate problem of physical injuries caused by defective products.
Where the parties were in contractual privity, warranty law provided the best
route for recovery of economic damages, but courts had to consider how to deal
with this type of damages for parties who did not enjoy contractual privity.[272] From this inquiry came the economic loss
rule; Florida courts determined that “a manufacturer in a commercial
relationship has no duty under either a negligence or strict products liability
theory to prevent a product from injuring itself.”[273]
The economic loss rule was widely applied
with certain exceptions to cases in which the parties were in contractual
privity and one party sought to recover damages in tort for matter arising
under the contract. This expansion of the rule created confusing and
inconsistent precedent amongst Florida Courts. The Florida Supreme Court
recently revisited the economic loss rule and its application in Tiara Condominium Association v. Marsh &
McLennan Cos.[274]
In Tiara,
the Florida Supreme Court addressed the following certified question: “Does the
economic loss rule bar an insured’s suit against an insurance broker where the
parties are in contractual privity with one another and the damages sought are
solely for economic losses?”[275] The court not only answered in the negative
but the held that “the application of the economic loss rule is limited to
products liability cases. Therefore, we recede from prior case law to the
extent that it is inconsistent with this holding.”[276] In arriving at this decision, the Florida
Supreme Court noted the ever-expanding application of the economic loss rule
and discussed the prior application of the economic loss rule to parties in
contractual privity and to parties not in privity. The Florida Supreme Court
noted that contractual privity provided actions based on breach of warranty for
economic damages.[277] Determining that parties not in privity may
seek recovery under warranty claims for defective products under current law,
the Florida Supreme Court held, “In exchange for eliminating the privity
requirements of warranty law and expanding the tort liability for manufacturers
of defective products which cause personal injury, we expressly limited tort
liability with respect to defective products to injury caused to persons or
damage caused to property other than the defective product itself.”[278] The Florida Supreme Court concluded,
holding, “Having reviewed the origin and original purpose of the economic loss
rule, and what has been described as the unprincipled extension of the rule, we
now take this final step and hold that the economic loss rule applies only in
the products liability context. We thus recede from our prior rulings to the
extent that they have applied the economic loss rule to cases other than
products liability.”[279]
Following this opinion, confusion permeated
the courts with respect to whether the heavily relied upon rule still applied
in the context of construction defect litigation.[280] This discussion begins with the Florida Supreme
Court’s opinion in Casa Clara Condominium Association v. Charley Toppino
& Sons, 620 So. 2d 1244 (Fla. 1993). Defining what qualifies as a
product with respect to a construction project, the Florida Supreme Court, in Casa
Clara, disagreed that “other property” included “individual components and
items of building material.”[281] Rather, the court reasoned,
to determine the character of a loss, one
must look to the product purchased by the plaintiff, not the product sold by
the defendant. Generally, house buyers have little or no interest in how or
where the individual components of a house are obtained. They are content to
let the builder produce the finished product, i.e., a house. These homeowners
bought finished products—dwellings—not the individual components of those
dwellings. They bargained for the finished products, not their various
components.[282]
This precedent is nothing solely attributable
to the Casa Clara opinion. For
example, the Casa Clara court cited
the Virginia Supreme Court’s holding in Sensenbrenner
v. Rust, Orling &Neale Architects, Inc., 374 S.E. 2d 55 (Va. 1988).[283] In Sensenbrenner,
the plaintiff homeowner entered into a contract with a general contractor for
the construction of a new home with an enclosed swimming pool.[284] The contractor contracted with, among
others, an architect and a pool subcontractor.[285] Upon completion, the contractor conveyed the
property to the homeowner.[286] Subsequently, the pool settled, rupturing
water pipes.[287] The homeowner brought a claim for negligent
design and supervision against the architect, and negligent construction
against the pool contractor.[288] Affirming dismissal of the tort claims, the
Virginia Supreme Court held:
Although sales of real estate are not
controlled by product liability concepts in other respects, the rule limiting
recovery for economic losses to the law of contracts does apply to sales of
real property alleged to be qualitatively defective. Tort law is not designed,
however, to compensate parties for losses suffered as a result of a breach of
duties assumed only by agreement. . . .
The controlling policy consideration
underlying tort law is the safety of persons and property—the protection of
persons and property from losses resulting from injury. The controlling policy
consideration underlying the law of contracts is the protection of expectations
bargained for. If that distinction is kept in mind, the damages claimed in a
particular case may more readily be classified between claims for injuries to
persons or property on one hand and economic losses on the other.
The plaintiffs here alleged nothing more than
disappointed economic expectations. They contracted with a builder for the
purchase of a package. The package included land, design services, and
construction of a dwelling. The package also included a foundation for the dwelling,
a pool, and a pool enclosure. The package is alleged to have been defective . .
. . This is a purely economic loss, for which the law of contracts provides the
sole remedy.
Recovery in tort is available only when there
is a breach of a duty “to take care for the safety of the person or property of
another.” The architect and the pool contractor assumed no such duty to the
plaintiffs by contract, and the plaintiffs’ complaint alleges no facts showing
a breach of any such duty imposed by law.[289]
Moreover, in his concurring opinion in Indemnity Insurance Co. v. American
Aviation, Inc., 891 So. 2d 532, 544 (Fla. 2004), Justice Cantero referred
to the Supreme Judicial Court of Massachusetts’s holding in Berish v. Bornstein, 770 N.E. 2d 961,
975 (Mass. 2002), noting “damages sought, in tort, for economic losses from a
defective building are just as offensive to tort law as damages sought for
economic losses stemming from a defective product.”[290]
The Tiara
court specifically receded from its prior economic loss rule precedent to the
extent it was inconsistent with its holding.[291] Nothing inconsistent exists between Tiara refocusing the economic loss rule
as applicable only in the products liability context and the Casa Clara analysis defining buildings
and structures as products. The Tiara
decision impacts merely one sentence of the Casa
Clara opinion; where the majority notes, “The cases in conflict, Adobe, Drexel, and Latite,
incorrectly refused to apply the economic loss rule to what should have been
contract actions, and we disapprove them.”[292] As noted above, claims arising in products
liability are quintessentially claims in which the parties do not enjoy privity
of contract. This was the inherent premises of Tiara, and it is inconsistent with Tiara for the economic loss rule to apply in contract actions. The
rest of the Casa Clara decision
remains consistent with, and unaffected by, the Tiara ruling.[293]
The court recognized, however, for claims in
which the parties are in contractual privity, the independent tort doctrine
precludes parties from recasting causes of action in tort that are otherwise
breach of contract claims.[294] Although sometimes incorrectly referred to
as an “economic loss rule exception,” the independent tort doctrine provides
that in an action between parties in contractual privity, a plaintiff asserting
a tort claim must allege action beyond and independent of the breach of
contract, which amounts to an independent tort.[295] To set forth a claim in tort between parties
in contractual privity, a party must allege action beyond and independent of a
breach of contract that amounts to an independent tort.[296] Common pleading strategy provides that a
party may plead actions in the alternative; however, a tort claim fails as a
matter of law if it does not set forth a tort independent of a duty owed under
its contract.
F. Interest
Plaintiffs are generally entitled to recover
prejudgment interest on contract claims. In rare instances, plaintiffs will
also be able to recover prejudgment interest for non-contract cases if there
was an ascertainable loss that occurred at a specific time prior to the entry
of judgment.[297]
Generally, interest accrues on a Florida
judgment at the statutory rate set on December 1st of every year for the
following year by the Chief Financial Officer for the State of Florida.[298] The rate is calculated by averaging the
discount rate of the Federal Reserve Bank of New York for the preceding year,
then adding five hundred (500) basis points to the averaged federal discount
rate.[299]
G.
Punitive
Damages
Section 768.72, Florida Statutes (2019),
governs claims for punitive damages. Pursuant to the statute a claimant is not
entitled to punitive damages unless the claimant makes an evidentiary showing
that a reasonable basis for recovery of punitive damages exists.[300] In other words, punitive damages will not be
awarded if the claimant has not made a clear and convincing evidentiary showing
that the defendant was guilty of intentional misconduct or gross negligence.[301]
“Intentional misconduct” under the statute
means that the defendant had actual knowledge that the conduct was wrong and
created a high probability of injuring or causing damage to the claimant, but
despite that knowledge, intentionally pursued the same course of conduct; and
that conduct caused injury.[302] For a defendant’s conduct to rise to the
level of “gross negligence,” the conduct must be so reckless or careless that
it constituted a conscious disregard or indifference to the life, safety, or
rights of persons exposed to such conduct.[303]
Of note, employers, principals, corporations
and other legal entities are only liable for punitive damages if “intentional
misconduct” or “gross negligence” has been shown, and one of the following is
shown: (a) the employer, principal, corporation or other legal entity actively
and knowingly participated in such conduct; (b) the officers, directors, or
managers of the employer, principal, corporation, or other legal entity
knowingly condoned, ratified, or consented to such conduct; or (c) the
employer, principal, corporation, or other legal entity engaged in conduct that
constituted gross negligence and contributed to the loss, damages, or injury
suffered by the claimant.[304]
Nevertheless, Florida does cap punitive
damages awards under certain circumstances.[305] Where the fact finder determines that at the
time of injury the defendant had specific intent to harm the claimant and
determines that the defendant’s conduct did in fact harm the claimant, there is
no cap on punitive damages.[306] Where the fact finder determines that
wrongful conduct was motivated solely by unreasonable financial gain and
determines that the unreasonably dangerous nature of the conduct together with
the high likelihood of injury was actually known, the punitive damages award
may not exceed the greater of four (4) times the amount of compensatory damages
awarded to each claimant or $2 million.[307] Otherwise, an award of punitive damages may
not exceed the greater of three (3) times the amount of compensatory damages awarded
to each claimant or $500,000.[308]
Application of this section operates on a
post-judgment basis, and the jury may neither be instructed nor informed of
these caps.[309] Further, a claimant’s attorneys’ fees, if
payable based upon the judgement, are, to the extent that the fees are based on
a punitive damages award, calculated based on the final judgment for punitive
damages.[310]
H. Liquidated Damages
Liquidated damages are enforceable as long as
the assessment of actual damages as of the time of making the contract is
uncertain and the provision for liquidated damages is not strictly a penalty.[311]
There is no strict objective rule for
determining whether a sum stipulated for breach of contract is a penalty.
Courts take into account the reasonableness of the provisions, the certainty of
establishing actual damages, and the intent of the parties.[312] The determination of whether liquidated
damages are enforceable, or unenforceable as a penalty, is a question of law
for the court.[313] In determining whether liquidated damages
operates as a penalty, the amount of damages is analyzed for reasonableness.[314] Liquidated damages must not be so grossly
disproportionate to any damages that might reasonably be expected to follow
from a breach to show that the parties could only have intended to induce full
performance, rather than to liquidate their damages.[315] If the liquidated damages are unreasonable,
the courts will consider the damages to be a penalty and will not enforce them.[316] Where it is doubtful whether a contract clause
is a penalty or liquidated damages, the court will construe the payment of an
arbitrary sum as a penalty.[317]
If a contract calls for a party to be able to
elect to have liquidated damages or actual damages, the liquidated damage
clause may be considered to be a penalty and unenforceable.[318] Further, where a contract grants one party
the option of liquidated damages or actual damages, such language demonstrates
that the liquidated damages are an invalid penalty and will not be enforced.[319]
Liquidated damages for delay and loss of use
can be assessed in addition to actual damages for defects. However, liquidated
damages will not be assessed in addition to actual damages where only
liquidated damages are provided for in the contract.[320]
Parties should be cautious of the terms of
prime contracts versus subcontracts when liquidated damages are concerned. For
example, a subcontractor who actually causes a delay may not be held liable for
liquidated damages assessed against a contractor if the subcontract contains no
liquidated damages provision.[321] A pass through provision may similarly allow
liquidated damages for a period of delay caused by a subcontractor to be passed
from the contractor to the subcontractor who caused the delay.[322]
IX.
Case
Law and Legislation Update
A.
Amendments to Florida
Rule of Civil Procedure 1.442 (Proposals for Settlement)
The
Florida Supreme Court issued an opinion on May 26, 2022, that amended the
Florida Rule of Civil Procedure 1.442 (the “Amendment”). The Amendment,
effective July 1, 2022, prohibits parties from including non-monetary terms in
their Proposals for Settlement.[323]
Previously, Rule 1.442 allowed the inclusion of nonmonetary terms, such as the
inclusion of a general release, as a condition of acceptance of a proposal for
settlement. The Amendment now aligns the substantive elements of Rule 1.442
with those of Florida Statutes § 768.79, which permits parties to state the
total amount of the settlement and the amount offered to settle a claim for any
punitive damages with no reference to the inclusion of nonmonetary terms.[324]
The
specific changes within Rule 1.442 are found in Sections (c)(2)(C)-(D). Prior
to the Amendment, Section (c)(2)(C) stated that
“any relevant conditions” may be included in a settlement proposal.[325]
That language was stricken from the Rule, which now states that a proposal
shall “exclude nonmonetary terms.”[326]
However, it provides for exceptions “of a voluntary dismissal of all claims
with prejudice and any other nonmonetary terms permitted by statute.”[327]
The most notable example of a statute that permits nonmonetary terms in
settlement offers is Florida Statutes § 70.001(4)(c).[328]
This section includes nonmonetary terms that governmental entities may include
in settlement offers whenever government action “inordinately burdens private
property rights.”[329]
The second, and final, change to Rule 1.442 is found in Section (c)(2)(D).[330]
The Amendment keeps the language that the proposal must state the total amount
sought but strikes out the allowance of all nonmonetary terms.[331]
Prior
to the Amendment, there had been multiple issues with Rule 1.442. First, the
lack of uniformity with Florida Statutes § 768.79 caused a wealth of confusion
in the years since Rule 1.442 was first enacted in 1972. Since then, Rule 1.442
had been repealed and amended numerous times. The Florida Supreme Court
previously followed the premise that “a procedural rule should not be strictly
construed to defeat a statute it is designed to implement.”[332] Rather, the rule should be construed only to
the extent that it implements the requirements of the statute.[333]
Next,
the new language in these sections may also help cure any excessive ambiguity
associated with the Rule. For instance, in May 2022, Florida’s Fourth District
Court of Appeal noted that prior to the Amendment, Rule 1.442(c)(2)(D) required
that a settlement “state with particularity any relevant
conditions[,] . . . all nonmonetary terms of the proposal[, and] . .
. the amount proposed to settle a claim for punitive damages, if any.”[334]
Further, the court understood “particularity” to mean “the settlement proposal
be sufficiently clear and definite to allow the offeree to make an informed
decision without needing clarification.”[335]
With this requirement for particularity now excluded in Section (c)(2)(C) and
(c)(2)(D), courts will no longer be required to delve into an analysis on the
definitiveness of the terms of the settlement. Rather, the Amendment now simply
requires the total amount of the proposal to be stated and that no nonmonetary
terms be sought.
Finally,
the Amendment neuters the effectiveness of the proposal from the defense
perspective, because many carriers and businesses rightfully will not be keen
to offer significant money with the return of a general release, a requirement
of confidentiality, or indemnity from unpaid liens or other claimants to the
settlement proceeds. Unfortunately, with the change in the Rule, these
non-monetary terms are no longer permissible and including them will likely
lead to arguments that a Proposal for Settlement served after the amended Rule
goes into effect on July 1, 2022, that includes non-monetary conditions is void
and unenforceable.
B. Amendments
to Florida Rule of Civil Procedure 1.510 (Summary Judgment)
On May
1, 2021, the Florida Supreme Court’s amendment of Florida
Rule of Civil Procedure 1.510 (the “Amendment”) became effective. The
Amendment was done with the intent to align Florida’s summary judgement
standard with that of Federal Rule of Civil Procedure 56.[336]
The main implications of the Amendment relate to the timing and chronology of
filing a motion for summary judgement, the required response time for the
non-movant, and the non-movant no longer having to “disprove” the non-movant’s
case to succeed.
First,
regarding the timing and chronology of filing a motion for summary judgement
and the required response from the non-movant, section (b) of the Rule now
states that “a party may move for summary judgement at any time after the
expiration of 20 days from the commencement of the action or after service of a
motion for summary judgement by the adverse party.”[337]
Additionally, a movant must serve the motion at least 40 days before the time
fixed for the hearing.[338]
Once served, the nonmovant now must respond with its supporting factual
position at least 20 days before the hearing, once set.[339]
The Amendment continues to tie filing deadlines to the date of a hearing, but
these timing provisions now “allow for more deliberative consideration of
summary judgement motions.”[340]
In
June 2022, Florida’s Fourth District Court of Appeal ruled on the implication
of the required response by the non-movant at least 20 days before trial. In
that case, the defendant failed to file a response with their supporting
factual position.[341]
Despite that, they claimed that their prior summary judgement motion, which was
disposed of seven months before plaintiff filed their motion, satisfied the
requirement of Rule 1.510 (c)(5).[342]
The court ruled that the use of the word “must” in this section, solidified the
filing of a response mandatory.[343]
Further, the court declined to hold that the defendant’s prior motion for
summary judgement satisfied the requirement because, as it noted, the amended
rule states that the court “need only consider the cited materials.”[344]
Thus, the court was not required to consider other materials on the record when
ruling on the plaintiff’s motion for summary judgement under the Amendment.[345]
Next,
the Amendment makes a notable change in no longer requiring the moving party to
disprove the non-movant’s case in order for their motion for summary judgement
to be granted. The Florida Supreme Court adopted the summary judgement standard
and principles established in the so-called Celotex trilogy of federal
summary judgment case law. This trilogy refers to: Celotex
Corp. v. Catrett, 477 U.S. 317 (1986); Anderson v. Liberty Lobby,
Inc., 477 U.S. 242 (1986); and Matsushita Elec. Indus. Co. v. Zenith Radio
Corp. Under Celotex and the Amended Rule 1.510, a movant can now
satisfy its initial burden of production in two ways:
“If
the nonmoving party must prove X to prevail [at trial], the moving party at
summary judgement can either produce evidence that X is not so or point out
that the nonmoving party lacks the evidence to prove X.”[346]
“A
movant for summary judgement need not set forth evidence when the nonmovant
bears the burden of persuasion at trial.”[347]
The
Supreme Court further explained that the test for the existence of a genuine
factual dispute is whether “the evidence is such that a reasonable jury could
return a verdict for the moving party.” Anderson, 477 U.S. at 248.
Moreover, it will no longer be plausible to maintain that “the existence of any
competent evidence creating an issue of fact, however credible or incredible,
substantial, or trivial, stops the inquiry and precludes summary of judgment,
so long as the ‘slightest doubt’ is raised.[348]
Finally,
the Florida Supreme Court amended rule 1.510(a) to state that the court shall
state its reasons for granting or denying a summary judgement motion on the
record.[349]
This wording goes a step further than Federal Rule 56(a), which states the
court should state its reasons on the record.[350]
In order to comply with this requirement, the court must provide enough
specificity in its reasons to provide “useful guidance to the parties and, if
necessary, to allow for appellate review.”[351]
This stringent requirement was enacted to ensure that Florida courts “embrace
the federal summary judgement standard in practice and not just on paper.”[352]
C. Spring
Isle Opinion (Statute of Repose Triggering Events)
Spring
Isle Community Association, Inc. v. Herme Enterprises, Inc. is a
2021 decision from Florida’s Fifth District Court of Appeal with significant
analysis regarding Florida’s ten-year statute of repose for construction
litigation pursuant to Florida Statutes § 95.11(3)(c).
Developer
and general contractor, Pulte Home Company (“Pulte”), developed a portion of
Spring Isle with 71 buildings comprising 390 townhome units.[353]
Approximately 10 years after the development was completed, the Association
sued Pulte for alleged defects primarily related to building exterior envelopes.[354]
Subsequently, Pulte sent notices of claims pursuant to Florida Statutes Section
558.004 to its subcontractors, including Herme Enterprises, Inc. (“Herme”), before
filing third-party claims against them.[355]
After
discovery, Herme filed an amended motion for partial summary judgement as to
Pulte’s third-party causes of action “arguing that the ten-year repose period
as to each Spring Isle townhome unit commenced when the certificate of
occupancy was issued for such unit.”[356]
Herme won its motion for partial summary judgement, which Pulte appealed. After
a settlement between Pulte and the Association, Pulte assigned its rights and
causes of action to the Association, including its pending appeal.[357]
Florida
Statutes Section 95.11(3)(c), states that any action regarding the design,
planning, or construction of an improvement to real property must:
“be
commenced within ten-years after the date of actual possession by the owner,
the date of issuance of a certificate of occupancy, the date of abandonment of
construction if not completed, or the date of completion or termination of the
contract between the professional engineer, registered architect, or licensed
contractor and his or her employer, whichever date is latest.”[358]
The disagreement between the Association and Herme centered
on which of the triggering events for the ten-year statute of repose occurred
last. Herme argued, and the trial court agreed, that the repose period was
individualized for each unit and commenced on a rolling basis as the
certificates of occupancy were issued for each. On the other hand, the
Association argued that the completion date of the entire contract between the
Pulte and Herme triggered the repose period. The completion date occurred less
than ten-years before Pulte filed its third-party complaint.
Pulte and Herme entered into a master services agreement in
May 2004 that merely provided that Herme was to perform stucco work for Pulte.[359] The
trial court noted that this agreement was extremely broad. The agreement did
not specify a duration, payment amount, or the work to be performed, but rather
was to apply to any Pulte project in its Orlando division.[360]
Further, the agreement stated that Pulte’s obligation to issue written job
orders was on a “house-to-house and/or building-to-building basis” and that “[c]ommencement
of work by [Herme] on a house or building listed in said work orders constitutes
acceptance of terms and conditions contained in this Agreement.”[361]
The agreement also included two “schedules,” one for each
phase of the Spring Isle project.[362]
However, the schedules made no mention of what townhome buildings, models, or
units to which Herme would apply stucco in each subdivision of Spring Isle.
There was, however, an “Effective Date Range” for the project from 1/21/05 to
12/31/09.[363]
The trial court concluded “that the Schedule[s] combined
with the terms set forth in the Master Agreement constituted a contract between
Pulte and Herme for statute of repose purposes.”[364]
However, it further determined that because the contract did not actually
require Herme to perform work on any particular townhouse, the contract should
be deemed complete when Pulte made the final payment for each unit.[365] The
trial court thereafter determined that the appropriate triggering event was the
date of issuance of a certificate of occupancy because Pulte’s payment records
reflected payments for each unit after Herme completed its work (rendering the
contract for that unit “complete”), and that the payments were made prior to
the issuance of each certificate of occupancy.[366]
In its opinion, Fifth DCA took a different view of the
contract completion dates. Herme argued that each work order issued by Pulte created
a separate contract. However, because there were no work orders in the
appellate record, it was not conclusive whether each work order for each unit
constituted a separate contact or whether they were a part of a larger
agreement.[367]
Further, the fact that Pulte made payments to Hermer after it completed its
stucco work did not necessarily constitute a “final payment” as the trial court
suggested.[368]
In addition, Herme’s argument that the work orders signified separate contracts
contradicted the trial court’s finding that “the contract between Pulte and
Herme was the Schedule[s] together with the terms set forth in the master
agreement.”[369]
Ultimately, the court held that the evidence was insufficient to determine the
number of contracts that existed between Pulte and Herme or the contract
completion dates.[370]
Because the contract completion dates may have extended past the issuance of
certificates of occupancy, there was a genuine issue of fact as to which
triggering event was the last to occur, and summary judgment was overturned.[371]
D.
The Statutory Civil Action – Amendments
to Fla. Stat. §553.84
In Florida, a
statutory cause of action exists for any person or party in an individual
capacity or on behalf of a class of persons or parties damaged as a result of a
violation of the Florida Building Codes Act[372]
or the Florida Building Code.
Prior to the
Act, theoretically any violation could give rise to the Statutory Civil
Action. Post April 13, 2023, the Statutory Civil Action is limited to material
violations of the Florida Building Codes Act or the Florida Building Code.[373]
To avoid confusion as to what constitutes a “material violation” for the
purposes of the Statutory Civil Action, the Act now provides a definition of
what constitutes a material violation:
For purposes of
this section, the term “material violation” means a Florida Building Code Violation
that exists within a completed building, structure, facility which may
reasonably result, or has resulted, in physical harm to a person or significant
damage to the performance of a building or its systems.[374]
The Statutory
Civil Action is further curbed by the amendments made to §95.11(3)(c), Fla.
Stat. Notably, the limitation periods set forth in §95.11(3)(c), Fla.
Stat. now apply to any action commenced on or before April 13, 2023,
regardless of when the cause of action accrued. However, an important caveat
exists here: any action that would not have been barred under §95.11(3)(c), Fla.
Stat., before the amendments made by the Act, must be commenced on or
before July 1, 2024, or else it is barred.[375]
[1] As to miscellaneous liens,
see §§ 713.50 to 713.79, Florida Statutes (2019).
[2] As to construction liens,
see §§ 713.001 to 713.37, Florida Statutes (2018).
[3] See Trytek v. Gale
Indus., Inc., 3 So. 3d 1194, 1199 (Fla. 2009). Compare, Stunkel
v. Gazebo Landscaping Design, Inc., 660 So.2d 623, 625–26 (Fla.1995)
(noting that strict compliance with Construction Lien Law’s time requirements
is necessary because “[c]ontracting parties need certainty about when time
periods for notification begin”); with Premier Finishes, Inc. v. Maggirias,
130 So. 3d 238, 242 (Fla. 2d DCA 2013) (“[A]bsent a showing of prejudice, a
deficiency, error, or omission will not invalidate the [construction] lien.”)
(citing Johnson & Bailey Architects P.C. v. Se. Brake Corp., 517
So.2d 776, 778 (Fla. 2d DCA 1988)).
[4] CDS & Assocs. of
Palm Beaches, Inc. v. 1711 Donna Rd. Assocs., Inc., 743 So. 2d 1223, 1225
(Fla. 4th DCA 1999); see also Niehaus v. Big Ben’s Tree Serv., Inc.,
982 So. 2d 1253, 1254 (Fla. 1st DCA 2008) (“[A] construction lien can arise
only when a valid contract exists between the parties […and] [in FN1] [a]
contract implied in law is not a contract at all, but a legal fiction hinging
on the concept of unjust enrichment;” thus, no lien can arise).
[5] § 713.01(23), (26), Fla.
Stat. (2019).
[6] § 255.05, Fla. Stat. (2019).
[7] § 713.10 (1), Fla. Stat.
(2019).
[8] § 713.10 (2)-(3), Fla.
Stat. (2019).
[9] See 713.01(18),
Fla. Stat. (2019) (defining a “Lienor” as a “person” who is a contractor;
subcontractor; sub-subcontractor; laborer; materialman who contracts with the
owner, contractor, subcontractor, or sub-subcontractor; or a professional
lienor and includes his or her successor in interest. Professional lienors,
including design professionals, are further defined under section 713.03,
Florida Statutes (2019)).
[10] § 713.01(16), Fla. Stat.
(2019) (“‘Laborer’ means any person other than an architect, landscape
architect, engineer, surveyor and mapper, and the like who, under properly
authorized contract, personally performs on the site of the improvement labor
or services for improving real property and does not furnish materials or labor
service of others.”).
[11] § 713.01(20), Fla. Stat.
(2019) (“‘Materialman’ means any person who furnishes materials under contract
to the owner, contractor, subcontractor, or sub-subcontractor on the site of
the improvement or for direct delivery to the site of the improvement or, for
specially fabricated materials, off the site of the improvement for the
particular improvement, and who performs no labor in the installation
thereof.”).
[12] § 713.01(8), Fla. Stat. (2019) (“‘Contractor’ means a
person other than a materialman or laborer who enters into a contract with the
owner of real property for improving it, or who takes over from a contractor as
so defined the entire remaining work under such contract [and] . . . includes
an architect, landscape architect, or engineer who improves real property pursuant
to a design-build contract . . . .”).
[13] § 713.01(28), Fla. Stat.
(2019) (“‘Subcontractor’ means a person other than a materialman or laborer who
enters into a contract with a contractor for the performance of any part of
such contractor’s contract, including the removal of solid waste from the real
property. The term includes a temporary help firm as defined in [section
443.101, Florida Statutes (2019)]”).
[14] § 713.01(29), Fla. Stat.
(2019) (“‘Sub-subcontractor’ means a person other than a materialman or laborer
who enters into a contract with a subcontractor for the performance of any part
of such subcontractor’s contract, including the removal of solid waste from the
real property. The term includes a temporary help firm as defined in [section
443.101, Florida Statutes (2019)]”).
[15] § 713.04, Fla. Stat. (2019).
[16] § 713.03, Fla. Stat. (2019).
[17] § 489.128(2), Fla. Stat.
(2019).
[18] Compare § 713.05, Fla. Stat. (2019) (addressing liens of
persons in privity of contract with the owner); with § 713.06, Fla.
Stat. (2019) (addressing liens of persons not in privity of contract with the
owner).
[19] See § 713.13, Fla.
Stat. (2019).
[20] See § 713.13(1)-(2),
Fla. Stat. (2019).
[21] See § 713.13(6),
Fla. Stat. (2019).
[22] § 713.13(1), Fla. Stat.
(2019).
[23] § 713.06(2)(a), Fla.
Stat. (2019). But see Carter Sand Co., Inc. v. Baymeadows, Inc.,
320 So. 2d 14, 15 (Fla. 1st DCA 1975) (holding that in the case of a lienor
working below a subcontractor, notice must be served before final payment is
made to the subcontractor). The Carter precedent, however, is often criticized
as being in direct contention with the language of the statute. See, e.g.,
Tuttle/White Constructors, Inc. v. Hughes Supply, Inc., 371 So. 2d 559, 564
(Fla. 4th DCA 1979).
[24] § 713.06(2)(a), Fla.
Stat. (2019).
[25] § 713.03(3), Fla. Stat.
(2019).
[26] § 713.06(2)(a), Fla.
Stat. (2019).
[27] § 713.08(5), Fla. Stat.
(2019).
[28] Id. See § 713.01(12); (13), Fla. Stat. (2019),
(defining “final furnishing” and “furnish materials.”).
[29] § 713.22(1), Fla. Stat.
(2019). Should the 365th day fall on a Saturday, Sunday, or legal holiday, the
time period is
extended to the next
business day. Lehmann Dev. Corp. v. Nirenblatt, 629 So. 2d 1098, 1099
(Fla. 2d DCA 1994).
[30] § 713.22(2), Fla. Stat.
(2019).
[31] In the event a summons to
show cause is served, suit to enforce the lien must be filed within twenty (20)
days of
service of the summons. §
713.21(4), Fla. Stat. (2019).
[32] See, e.g., SAAD
Homes, Inc. v. Rivero, 23 So. 3d 862, 863 (Fla. 3d DCA 2009).
[33] Compare Citibank, N.A.
v. Villanueva, 174 So. 3d 612, 613 (Fla. 4th DCA 2015) (“The fee simple
title holder is an indispensable party in an action to foreclose a mortgage on
property.”); with Diversified Mortg. Inv’rs v. Benjamin, 345 So. 2d 392,
393 n.1 (Fla. 3d DCA 1977) (“The property owner is a necessary party at time of
suit to foreclose a mechanic’s lien.”) (citing Deltona Corp. v. Indian
Palms, Inc., 323 So. 2d 282, 283 (Fla. 2d DCA 1975); McGuire v. Consol.
Elec. Supply, Inc., 329 So. 2d 411, 412 (Fla. 4th DCA 1976)).
[34] Moore v. Leisure Pool
Servs., Inc., 412 So. 2d 392, 393 (Fla. 5th DCA 1982).
[35] Morris & Esher,
Inc. v. Olympia Enters., Inc., 200 So. 2d 579, 582 (Fla. 3d DCA 1967).
[36] Gorman Co. of Fort
Lauderdale, Inc. v. Frank Maio Gen. Contractor, Inc., 438 So. 2d 1018, 1019
(Fla. 4th DCA
1983) (citing Bybee v.
Stearn, 95 So. 2d 529, 531 (Fla. 1957)).
[38] See Marocco v. Brabec,
No. 1D17-894, 2019 WL 1498321, at *4 (Fla. 1st DCA Apr. 5, 2019) (holding the
trial court did not abuse discretion in denying an award for attorney’s fees
where the homeowner successfully defended the lien foreclosure but did not
prevail under Florida’s “significant issues” test amongst the other claims); see
also HHA Borrower, LLC. v. W.G. Yates & Sons Constr. Co., 266 So. 3d
1267, 1268 (Fla. 5th DCA 2019) (holding that, on equitable grounds, neither
party was entitled to attorneys’ fees, even where both prevailed on significant
issues).
[39] § 713.31(2)(c), Fla.
Stat. (2019). In Florida, the property
owner is also granted the right of an independent cause of action for the
filing of a fraudulent construction lien. Id.
[40] Argonaut Ins. Co. v.
May Plumbing Co., 474 So. 2d 212, 214 (Fla. 1985); Summerton v. Mamele,
711 So. 2d 131, 133 (Fla. 5th DCA 1998) (“The trial court has no discretion
with regard to awarding prejudgment interest and must do so applying the
statutory rate of interest in effect at the time the interest accrues.”).
[41] § 713.30, Fla. Stat. (2019).
[42] § 713.06(1), Fla. Stat.
(2019); see also Fernandez v. Manning Bldg. Supplies, Inc., No.
1D18-4819, 2019 WL 4655988, at *2 (Fla. 1st DCA Sept. 25, 2019) (distinguishing
interest accruing as a “delinquency charge” versus interest accruing as a
“financing charge”).
[43] § 713.20(2), Fla. Stat.
(2019).
[44] Id.
[45] § 713.20(4)-(5), Fla.
Stat. (2019); Stock Bldg. Supply of Fla., Inc. v. Soares Da Costa Const.
Servs., LLC, 76 So. 3d 313, 318 (Fla. 3d DCA 2011).
[46] § 337.18, Fla. Stat. (2019).
[47] § 255.05, Fla. Stat. (2019).
[48] § 337.18(1)(b), Fla.
Stat. (2019).
[50] Id.
[51] Id.
[52] § 337.18(1)(b), Fla.
Stat. (2019).
[53] § 337.18(1)(d), Fla.
Stat. (2019).
[54] § 337.18(1)(b), (d), Fla.
Stat. (2019).
[55] § 255.05(1), Fla. Stat.
(2019). Public bond statute voids venue or forum selection clauses. Travelers
Cas. & Ins. Co. of Am. v. Cmty. Asphalt Corp., 221 So. 3d 742, 743-44
(Fla. 3d DCA 2017).
[56] § 255.05(1)(b), Fla. Stat. (2019).
[57] § 255.05(2)(a)2, Fla.
Stat. (2019).
[58] Id.
[59] Id.
[60] Id.
[61] § 255.05(1)(c), Fla.
Stat. (2019).
[62] § 255.05(2)(a)2, Fla.
Stat. (2019).
[63] § 255.05(10), Fla. Stat.
(2019).
[64] The Florida Legislature
defined “completion of the contract” to mean, “the later of the date of final
performance of all the contracted services or the date that final payment for
such services becomes due without regard to the date final payment is made.” Fla.
Stat. § 95.11(3)(c) (2019). Prior to this Legislative enactment, completion
of the contract, according to a prior decision by Florida’s Fifth District
Court of Appeals, occurred when final payment was actually made to the
contractor. Cypress Fairway Condo. v.
Bergeron Const. Co. Inc., 164 So. 3d 706, 708 (Fla. 5th DCA 2015) (holding
that “completion of the contract means completion of performance by both sides
of the contract, not merely performance by the contractor. Had the legislature
intended the statute to run from the time the contractor completed performance,
it could have simply so stated. It is not our function to alter plain and
unambiguous language under the guise of interpreting a statute […].
Accordingly, we conclude that the statute of repose commenced to run on the
date of completion of the contract, which, in this case, was the date on which
final payment was made under the terms of the contract.”). By defining completion in this way, a party
could effectively extend another’s liability for construction defects by
delaying final payment.
[66] Id. See Covenant
Baptist Church, Inc. v. Vasallo Constr., Inc., 273 So. 3d 236 (Fla. 3d DCA
2019) (“Under Florida law, ‘[w]hen a newly finished roof leaks it is not only
apparent, but obvious, that someone is at fault.’”) (quoting Kelley v. Sch.
Bd. of Seminole Cty., 435 So.2d 804, 806 (Fla. 1983)).
[67] LIMITATION OF ACTIONS,
2018 Fla. Sess. Law Serv. Ch. 2018-97 (C.S.C.S.H.B. 875) (WEST).
[68] § 95.11(3)(c), Fla. Stat.
(2019) (“Counterclaims, cross-claims, and third-party claims that arise out of
the conduct, transaction, or occurrence set out or attempted to be set out in a
pleading may be commenced up to 1 year after the pleading to which such claims
relate is served, even if such claims would otherwise be time barred.”).
[69] Id. This amendment
essentially codified long-standing Florida case law rejecting the “continuous
treatment” doctrine for construction defect claims. See Sch. Bd. of Seminole
County v. GAF Corp., 413 So. 2d 1208, 1211–12 (Fla. 5th DCA 1982), quashed
sub nom. Kelley v. Sch. Bd. of Seminole County, 435 So. 2d 804 (Fla. 1983).
Pursuant to the continuous treatment doctrine, the accrual of a malpractice
cause of action is suspended until treatment ends or the professional
relationship is terminated. Id. (describing the doctrine in the
construction context as, when a person, “relying upon a ‘professional’ to
resolve and cure a problem within the ambit of their professional relationship,
and where the professional continuously works on the problem and assures the
client the problem is being solved,” makes the issue of when that person knew
or should have known his problem was permanent and irreparable, a question of
fact).
[70] Dubin v. Dow Corning
Corp., 478 So. 2d 71, 73 (Fla. 2d DCA 1985) (“A special statute of
limitations which addresses itself to specific matters takes precedence over a
general statute.”); see also Brock v. Garner Window & Door Sales, Inc.,
187 So. 3d 294, 295 (Fla. 5th DCA 2016) (holding that work performed by
unlicensed contractor still subject to four-year statute of limitations founded
on construction or an improvement to real property).
[71] § 95.11(4)(a), Fla. Stat.
(2019).
[72] Pensacola Executive
House Condo. Ass’n, Inc. v. Baskerville-Donovan Eng’rs, Inc., 566 So. 2d
850, 853 (Fla. 1st DCA 1990), aff’d 581 So. 2d 1301 (Fla. 1991).
[73] § 95.11(2)(b), Fla. Stat.
(2019).
[74] § 95.11(3).
[75] § 95.11(4)(d).
[76] § 95.11(5)(a), (b).
[77] Nat’l Auto Serv.
Ctrs., Inc. v. F/R 550, LLC, 192 So.3d 498, 509 (Fla. 2d DCA 2016) (quoting
Univ. of Miami v. Bogorff, 583 So..2d 1000, 1003 (Fla. 1991), modified on
other grounds by Tanner v. Hartog, 618 So.2d 177, 181 (Fla. 1993)).
[78]
§95.11(3)(c), Fla Stat. (prior to April 13, 2023).
[79] See §95.11(3)(c), Fla.
Stat. Emphasis added.
[80] §95.11(3)(c), Fla
Stat. (prior to April 13, 2023). Emphasis added.
[81] § 95.11(3)(c), Fla.
Stat. Emphasis added.
[82] Id. Emphasis
added.
[83] Busch v. Lennar Homes,
LLC, 219 So. 3d 93, 96 n.2 (Fla. 5th DCA 2017), reh’g denied (May
30, 2017) (rejecting the argument that service of a Chapter 558 notice tolled
the statute of repose for construction defect claim because if filed
prematurely the lawsuit would merely have been stayed, not dismissed); but
see, infra footnote 79.
[84] Gindel v. Centex Homes,
267 So. 3d 403, 407 (Fla. 4th DCA 2018).
Upon the Court’s order granting the appellees’ motion for certification
of conflict, the Fourth District Court of Appeal certified the following
question to the Florida Supreme Court:
DOES COMPLIANCE
WITH THE [pre-suit] NOTICE REQUIREMENT UNDER SECTION 558.004(1), FLORIDA
STATUTES (2014) CONSTITUTE THE COMMENCEMENT OF A CIVIL ACTION OR PROCEEDING
SUFFICIENT TO TOLL THE STATUTE OF REPOSE SET FORTH IN SECTION 95.11(3)(C),
FLORIDA STATUTES (2014)?
272 So.
3d 417 (Fla. 4th DCA 2019).
[85] Manney v. MBV Eng’g,
Inc., 273 So. 3d 214, 215-17 (Fla. 5th DCA 2019)
[86] Id.
[87] Id.
[89] § 558.001.
[90] § 558.002(3).
[91] Id.
[92] § 558.002(1).
[93] § 558.002(5).
[94] § 558.004(12).
[95] §
558.003. But see, Banner Supply Co. v. Harrell, 25 So. 3d 98, 100 (Fla. 3d
DCA 2009) (denying certiorari and petition for writ of mandamus as to trial
court’s refusal to abate action where plaintiff did not comply specifically
with Chapter 558 because abatement would have been futile to the purpose of the
pre-suit notice requirements).
[96] § 558.004(14).
[97] §§ 558.003; 558.004(7). But
see, Banner Supply Co. v. Harrell, 25 So. 3d 98, 100 (Fla. 3d DCA 2009)
(denying certiorari and petition for writ of mandamus as to trial court’s
refusal to abate action where plaintiff did not comply specifically with
Chapter 558 because abatement would have been futile to the purpose of the
pre-suit notice requirements).
[98] § 558.004(1)(a).
[99] Id.
[100] § 558.004(1)(b).
[101] § 558.004(1)(c).
[102] § 558.004(2). The
statute further incorporates a claimant’s corresponding duty to reasonably
accommodate access and inspections. Id. (“The claimant shall provide . .
. reasonable access to the property during normal working hours to inspect the
property to determine the nature and cause of each alleged construction defect
and the nature and extent of any repairs or replacements necessary to remedy
each defect. The person served with notice under subsection (1) shall
reasonably coordinate the timing and manner of any and all inspections with the
claimant to minimize the number of inspections.”).
[103] Id.
[104] § 558.004(5).
[105] Id.
[106] § 558.004(3).
[107] Id.
[108] § 558.004(4).
[109] Id.
[110] Id.
[111] § 558.004(15).
[112] Id.
[113] Id.
[114] § 558.004(6).
[115] § 558.004(7).
[116] § 558.004(10).
[117] See Gindel v. Centex Homes, 267 So. 3d 403
(Fla. 4th DCA 2018).
[118] § 558.004(13).
[119] Altman Contractors,
Inc. v. Crum & Forster Specialty Ins. Co., 232 So. 3d 273 (Fla. 2017).
[120] Id. at 277-78.
[121] Id. at 279.
[122] Id.
[123] Morgan Intern.
Realty, Inc. v. Dade Underwriters Ins. Agency, Inc., 617 So. 2d 455, 457
(Fla. 3d DCA 1993).
[124] Baron Oil Co. v.
Nationwide Mut. Fire Ins. Co., 470 So. 2d 810, 813 (Fla. 1st DCA 1985).
[125] Id. at 814.
[126] Id. at 813-14.
[127] IDC Const., LLC. v.
Admiral Ins. Co., 339 F. Supp. 2d 1342, 1349 (S.D. Fla. 2004) (citing Grissom
v. Commercial Union Ins. Co., 610 So. 2d 1299, 1307 (Fla. 1st DCA 1992); Klaesen
Bros., Inc. v. Harbor Ins. Co., 410 So. 2d 611 (Fla. 4th DCA 1982)).
[128] IDC Const., LLC,
339 F. Supp. 2d at 1349.
[129] Id.
[130] Swire Pacific
Holdings, Inc. v. Zurich Ins. Co., 845 So. 2d 161, 165 (Fla. 2003);
Rigby v. Underwriters at Lloyds, London, 907 So. 2d 1187, 1181, n.1 (Fla.
3d DCA 2005).
[131] Bethel v. Sec. Nat’l
Ins. Co., 949 So. 2d 219, 222 (Fla. 3d DCA 2006).
[132] Id.
[133] Id.
[134] Steil v. Florida
Physicians’ Ins. Reciprocal, 448 So. 2d 589, 592 (Fla. 2d DCA 1984).
[135] E. Fla. Hauling, Inc.
v. Lexington Ins. Co., 913 So. 2d 673, 678 (Fla. 3d DCA 2005).
[136] U.S. Concrete Pipe
Co. v. Bould, 437 So. 2d 1061, 1065 (Fla. 1983).
[137] Auto Owners Ins. Co.
v. Travelers Cas. & Sur. Co., 227 F. Supp. 2d 1248, 1265 (M.D. Fla.
2002) (citing Trizec Props., Inc. v. Biltmore Const. Co., 767 F.2d 810,
813 (11th Cir. 1985)); Carithers v. MidContinent Cas. Co., 782 F.3d
1240, 1247 (11th Cir. 2015).
[138] Auto Owners Ins. Co.,
227 F. Supp. 2d at 1266.
[139] Id.
[140] Id.
[141] Id.
[142] Id.
[143] See, e.g., Assurance
Co. of Am. v. Lucas Waterproofing Co., Inc., 581 F. Supp. 2d 1201, 1206
(S.D. Fla. 2008); N. River Ins. Co. v. Broward Cnty. Sheriff’s Office,
428 F. Supp. 2d 1284, 1289 (S.D. Fla. 2006);Auto Owners Ins. Co., 227 F.
Supp. 2d at 1266; Am. Motorists Ins. Co. v. Southern Sec. Life Ins. Co.,
80 F. Supp. 2d 1280, 1284 (M.D. Ala. 2000) (applying Florida law); Harris
Specialty Chems., Inc. v. U.S. Fire Ins. Co., Case No. 3:98–CV–351, 2000 WL
34533982 at *12 (M.D. Fla. 2000); Travelers Ins. Co. v. C.J. Gayfer’s &
Co., 366 So. 2d 1199 (Fla. 1st DCA 1979) (citing, inter alia, Prieto
v. Reserve Ins. Co., 340 So. 2d 1282 (Fla. 3d DCA 1977));but see Trizec
Props., Inc. v. Biltmore Const. Co., 767 F.2d 810, 813 n.6 (11th Cir. 1985)
(rejecting manifestation theory in context of duty to defend, but noting that
“We need not and do not decide whether [the insurer’s] theory … that damages
must manifest themselves . . . before coverage is triggered . . . is a correct
or incorrect statement of the law in general”).
[144] Axis Surplus Ins. Co.
v. Contravest Const. Co., 921 F. Supp. 2d 1338, 1346 (M.D. Fla. 2012).
[145] Id. at 1346-47
(citing Gayfer’s, 366 So. 2d at 1200).
[146] Id.
[147] Id.
[148] Id. (citing Gayfer’s,
366 So. 2d at 1201-02).
[149] Id. (citing Gayfer’s,
366 So. 2d at 1201 n.1.)
[150] Id. (citing Gayfer’s,
366 So. 2d at 1202) (“We find … that the phrase ‘caused by an occurrence’
informs the insured that an identifiable event other than the causative
negligence must take place during the policy period.”).
[151] Id.
[152] American Motorists
Ins. Co. v. Southern Security Life Insurance Co., 80 F. Supp. 2d 1280 (M.D.
Ala. 2000); Auto Owners Insurance Co. v. Travelers Casualty & Surety Co.,
227 F. Supp. 2d 1248 (M.D. Fla. 2002) (Report and Recommendation adopted by
district judge).
[153] See, e.g.,
Mid–Continent Cas. Co. v. Siena Home Corp., No. 5:08–CV–385–Oc–10GJK, 2011
WL 2784200, at *3 (M.D. Fla. July 8, 2011); Mid–Continent Cas. Co. v. CED
Constr. Partners, Ltd., 721 F. Supp. 2d 1209, 1216 (M.D.Fla.2010); Essex
Builders Grp., Inc. v. Amerisure Ins. Co., 485 F. Supp. 2d 1302, 1309 (M.D.
Fla. 2006).
[154] Axis Surplus Ins. Co.,
921 F. Supp. 2d 1338, 1348 (M.D. Fla. 2012).
[155] Id. (citing Trizec
Properties, Inc. v. Biltmore Const. Co., Inc., 767 F.2d 810, 812 (11th Cir.
1985)).
[156] Id. (citing Trizec
Properties, Inc., 767 F.2d at 812).
[157] Id. (citing Trizec
Properties, Inc., 767 F.2d at 813). See also, Carithers v. Mid-Continent
Cas. Co., 782 F.3d 1240, 1247 (11th Cir. 2015) (where the court expressed
“no opinion on what the trigger should be where it is difficult (or impossible)
to determine when the property was damaged”).
[158] See Paulucci v.
Liberty Mut. Fire Ins. Co., 190 F. Supp. 2d 1312, 1318 (M.D. Fla. 2002).
[159] Id.
[160] Id.
[161] Id.
[162] Sebo v. Am. Home
Assurance Co., Inc., 208 So. 3d 694, 698 (Fla. 2016), reh’g denied,
SC14-897, 2017 WL 361132 (Jan. 25, 2017); Paulucci, 190 F. Supp. 2d at
1319.
[163] Wallach v. Rosenberg,
527 So. 2d 1386, 1387 (Fla. 3d DCA 1988).
[164] Sebo, 208 So. 3d
at 697; Hartford Acc. & Indemn. Co. v. Phelps, 294 So. 2d 362, 364
(Fla. 1st DCA 1974).
[165] Arawak &
Aviation, Inc. v. Indemn. Ins., 285 F.3d 954, 958 (11th Cir. 2002).
[166] Id. at 956.
[167] Arawak &
Aviation, Inc. v. Indemn. Ins., 285 F.3d 954 (11th Cir. 2002).
[168] Id.
[169] Id.
[170] U.S. Fire Ins. Co. v.
J.S.U.B., Inc., 979 So. 2d 871 (Fla. 2007).
[171] Id. at 880.
[172] Id. at 882.
[173] Id.
[174] Id.
[175] Id. at 883.
[176] Id. at 888.
[177] Id.
[178] Id. at 889.
[179] Id.
[180] Id.
[181] Id.at 891.
[182] Auto-Owners Ins. Co.
v. Pozzi Window Co., 984 So. 2d 1241, 1243 (Fla. 2008).
[183] Id. at 1248-49.
[184] Id. at 1249.
[185] Gulf Ins. Co. v.
Continental Cas. Co., 464 So. 2d 207, 209 (Fla. 3d DCA 1985).
[186] Id. at 209-10.
[187] Towne Realty, Inc. v.
Safeco Ins. Co., 854 F.2d 1264, 1267 (11th Cir. 1988) (emphasis in
original).
[188] Twin City Fire Ins.
Co. v. Fireman’s Fund Ins. Co., 386 F. Supp. 2d 1272, 1278 (S.D. Fla.
2005).
[189] See Auto-Owners Ins.
Co. v. Palm Beach Cnty., 157 So. 2d 820, 822 (Fla. 2d DCA 1963); Twin
City Fire Ins. Co. v. Fireman’s Fund Ins. Co., 386 F. Supp. 2d 1272, 1278
(S.D. Fla. 2005) aff’d 200 Fed. Appx. 953 (11th Cir. 2006).
[190] See, e.g., Quinlan
Rental & Leasing, Inc. v. Linnel, 484 So. 2d 630, 632 (Fla. 2d DCA
1986) (explaining that an escape clause “avoids” responsibility for coverage); Auto-Owners
Ins. Co., 157 So. 2d at 822-24 (analyzing and collecting cases with escape
clauses and finding clause at issue was an escape clause where the clause was a
non-liability clause and utilized the exclusionary language providing that the
insurance “shall not apply. . .”); see also Maryland Cas. Co. v. Reliance
Ins. Co., 478 So. 2d 1068, 1071 (Fla. 1985) (explaining that other
insurance clause was a “classic ‘escape clause’” where it asserted it would
apply “only if there is no other valid and collectible insurance”); Continental
Cas. Co. v. Old Republic Ins. Co., No. 06-22628-CIV, 2007 WL 4365719 (S.D.
Fla. Dec. 11, 2007) (finding that policy contained an escape clause where it
provided “The insurance does not apply . . .”).
[191] See Allstate Ins. Co.
v. Executive Car & Truck Leasing, Inc., 494 So. 2d 487, 489 (Fla.
1986).
[192] See U.S. Fire Ins.
Co. v. Transportation Cas. Ins. Co., 747 So. 2d 404, 405 (Fla. 4th DCA
1999).
[193] See AIG Premier Ins.
Co. v. RLI Ins. Co., 812 F. Supp. 2d 1315, 1324-25 (M.D. Fla. 2011) (where
other insurance clauses are mutually repugnant, parties are liable for a pro
rata share of the settlement determined by policy limits); Certain
Underwriters at Lloyds, London Subscribing to Policy No. SA 10092-11581 v.
Waveblast Watersports, Inc., 80 F. Supp. 3d 1311, 1321 (S.D. Fla. 2015).
[194] See Argonaut Ins. Co.
v. Maryland Cas. Co., 372 So.2d 960 (Fla. 3d DCA 1979).
[195] Id.
[196] See, Porto Venezia
Condo. Ass’n, Inc. v. WB Fort Lauderdale, LLC, Case No. 11-60665-CIV, 2012
WL 12838283, at *3 (S.D. Fla. May 29, 2012) (“Equitable contribution allows for
co-guarantors to recover from one another if one of them has paid more than his
fair share.”).
[197] Zurich Am. Ins. Co.
v. S.-Owners Ins. Co., 314 F. Supp. 3d 1284, 1298 (M.D. Fla. 2018), aff’d,
770 Fed. Appx. 1009 (11th Cir. 2019) (quoting U.S. Fid. & Guar. Co. v.
Liberty Surplus Ins. Corp., Case No. 6:06–cv–1180–Orl–31UAM, 2007 WL
3275307, at *3 (M.D. Fla. Oct. 31, 2007)).
[198] § 558.004(1)(b), Fla.
Stat. (2019).
[199] Altman Contractors,
Inc. v Crum & Forster Specialty Ins. Co., 232 So. 3d 273 (Fla. 2017).
[200] Altman Contractors,
Inc. v. Crum & Forster Specialty Ins. Co., 124 F. Supp. 3d 1272, 1275
(S.D. Fla. 2015), rev’d in part, vacated in part, 880 F.3d 1300 (11th
Cir. 2018).
[201] Altman Contractors,
Inc., 232 So. 3d at 279.
[202] Sanislo v. Give Kids
the World, Inc., 157 So. 3d 256, 260 (Fla. 2015).
[203] See id. at 265; MVW Mgmt.,
LLC v. Regalia Beach Developers LLC, 230 So. 3d 108 (Fla. 3d DCA 2017), reh’g denied (Oct. 11, 2017).
[204] Fla. Dept. of Transp. v. V.E. Whitehurst & Sons, Inc., 636 So.
2d 101 (Fla. 1st DCA 1994).
[205] Fidelity & Guar. Ins. Co. v. Ford Motor Co., 707 F. Supp. 2d
1300 (M.D. Fla. 2010) (decided under Florida law); University Plaza Shopping Center v. Stewart, 272 So. 2d 507 (Fla.
1973); Gencor Industries, Inc. v.
Fireman’s Fund Ins. Co., 988 So. 2d 1206 (Fla. 5th DCA 2008); H & H Painting & Waterproofing Co.
v. Mechanic Masters, Inc., 923 So. 2d 1227 (Fla. 4th DCA 2006).
[206] Camp, Dresser & McKee, Inc. v. Paul N. Howard Co., 853 So. 2d
1072 (Fla. 5th DCA 2003).
[207] H & H Painting & Waterproofing Co., 923 So. 2d 1227 (Fla.
4th DCA 2006).
[208] Fidelity & Guar. Ins. Co., 707 F. Supp. 2d 1300; Park Central Hotel Co. v. Park Corp., 97
So. 2d 28 (Fla. 3d DCA 1957).
[209] Fidelity & Guar. Ins. Co., 707 F. Supp. 2d 1300.
[210] University Plaza Shopping Center, 272 So. 2d 507; Bankhead Welding Service, Inc. v. Florida
East Coast Ry., 240 So. 2d 648 (Fla. 3d DCA 1970); J. A. Jones Const. Co. v. Zack Co., 232 So. 2d 447 (Fla. 3d DCA 1970).
[211] Fidelity & Guar. Ins. Co., 707 F. Supp. 2d 1300.
[212] § 725.06, Fla. Stat.
(2019). Cuhaci & Peterson Architects,
Inc. v. Huber Const. Co., 516 So. 2d 1096 (Fla. 5th DCA 1987); Alonzo Cothron, Inc. v. Upper Keys Marine
Const., Inc., 480 So. 2d 136 (Fla. 3d DCA 1985).
[213] § 725.06. The monetary
limitation on the extent of the indemnification provided to the owner of real
property by any party in privity may not be less than one million
($1,000,000.00) dollars per occurrence unless otherwise agreed by the parties.
[214] § 725.06(1) (“However,
such indemnification shall not include claims of, or damages resulting from,
gross negligence, or willful, wanton or intentional misconduct of the
indemnitee or its officers, directors, agents or employees, or for statutory violation
or punitive damages except and to the extent the statutory violation or
punitive damages are caused by or result from the acts or omissions of the
indemnitor or any of the indemnitor’s contractors, subcontractors,
sub-subcontractors, materialmen, or agents of any tier or their respective
employees.”).
[215] § 725.08, Fla. Stat.
(2019).
[216] Apol v. Shaw, 647 So. 2d 139 (Fla. 1st DCA 1994); Cone Bros. Contracting Co. v.
Ashland-Warren, Inc., 458 So. 2d 851 (Fla. 2d DCA 1984).
[217] Team Land Development, Inc. v. Anzac Contractors, Inc., 811 So. 2d
698 (Fla. 3d DCA 2002).
[218] DEC Electric, Inc. v. Raphael Construction Corp., 53 So. 2d 427
(Fla. 4th DCA 1989), aff’d 558 So. 2d
427 (Fla. 1990).
[219] Snead Const. Corp. v. Langerman, 369 So. 2d 591 (Fla. 1st DCA
1978); Aetna Cas. & Sur. Co. v.
Warren Bros. Co., Division of Ashland Oil, Inc., 355 So. 2d 785 (Fla.
1978); Robert F. Wilson, Inc. v.
Post-Tensioned Structures, Inc., 522 So. 2d 79 (Fla. 3d DCA 1988); Charles R. Perry Const., Inc. v. C. Barry
Gibson & Assocs., Inc., 523 So. 2d 1221 (Fla. 1st DCA 1988); Team Land Dev., Inc. v. Anzac Contractors,
Inc., 811 So. 2d 698 (Fla. 3d DCA 2002); Everett Painting Co., Inc. v. Padula & Wadsworth Constr., Inc.,
856 So. 2d 1059 (Fla. 4th DCA 2003).
[220] Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc., 353 So.
2d 840 (Fla. 1977).
[221] G.E.L. Recycling, Inc. v. Atl. Envtl., Inc., 821 So. 2d 431 (Fla.
5th DCA 2002).
[222] See generally, WHO’S
RESPONSIBLE FOR A CONTRACTOR BEING INJURED OR KILLED ON YOUR COMMERCIAL
PROPERTY?, Michael J. Cox, Esq., THE BRIEFING: TAYLOR DAY LAW BLOG, Jul. 18
2019, available at
https://www.taylordaylaw.com/blog/whos-responsible-for-a-contractor-being-injured-or-killed-on-your-commercial-property/.
[223] Gory Associated Indus., Inc. v. Jupiter Roofing & Sheet Metal, Inc.,
358 So. 2d 93 (Fla. 4th DCA 1978).
[224] Hampton-Chrysler-Plymouth-Dodge, Inc. v. White, 448 So. 2d 87 (Fla.
1st DCA 1984).
[225] Truelove v. Blount, 954 So. 2d 1284 (Fla. 2d DCA. 2007).
[226] Zell v. Meek, 665 So. 2d 1048 (Fla. 1995); Bashaway v. Cheney Bros., Inc., 987 So. 2d 93 (Fla. 1st DCA 2008).
[227] U.S. v. Dempsey, 635 So. 2d 961 (Fla. 1994); Cousins Club Corp. v. Silva, 869 So. 2d 719 (Fla. 4th DCA 2004)
(explaining that damages are limited to the period of the child’s minority).
[228] Bidon v. Dep’t of Prof’l Regulation, 596 So. 2d 450, 452 (Fla.
1992). See also Price v. Tyler, 890
So. 2d 246, 250 (Fla. 2004); Pepper’s
Steel & Alloys, Inc. v. United States, 850 So. 2d 462, 465 (Fla. 2003);
State Farm Fire & Cas. Co. v. Palma,
629 So. 2d 830, 832 (Fla. 1993).
[229] Stockman v. Downs, 573 So. 2d 835 (Fla. 1991).
[230] See Jory v. Dep’t of Prof’l Regulation,
583 So. 2d 1075, 1077 (Fla. 1st DCA 1991).
[231] See id.; Aramark Unif. &
Career Apparel, Inc. v. Easton, 894 So. 2d 20, 26 (Fla. 2004).
[232] See, e.g., Succar v. Safra Nat’l Bank of New York, 237 Fed. Appx.
526, 529 (11th Cir. 2007); B & H
Constr. & Supply Co. v. District Bd. of Trustees of Tallahassee Cmty.
Coll., Fla., 542 So. 2d 382, 387 (Fla. 1st DCA 1989).
[233] Succar, 237 Fed. Appx. at 529.
[234] § 57.105(7), Fla. Stat.
(2019).
[235] Fallstaff Group, Inc. v. MPA Brickell Key, LLC, 143 So. 3d 1139,
1143 (Fla. 3d DCA 2014) (quoting Am.
& Foreign Ins. Co. v. Avis Rent–A–Car Sys. Inc., 401 So. 2d 855, 857
(Fla. 1st DCA 1981).
[236] Succar, 237 Fed. Appx. at 529.
[237] Sanislo v. Give Kids the World, Inc., 157 So. 3d 256, 260 (Fla.
2015).
[238] See id. at 265; MVW Mgmt.,
LLC v. Regalia Beach Developers LLC, 230 So. 3d 108 (Fla. 3d DCA 2017), reh’g denied (Oct. 11, 2017).
[239] MVW Mgmt., LLC, 230 So. 3d 108 (citing Order, Regalia Beach Dev. LLC v. MVW Mgmt. LLC, Case no. 16–3753 CA 22
(Fla. 11th Cir. June 30, 2016) (Hanzman, J.)).
[240] Succar, 237 Fed. Appx. at 528–29; Fallstaff Group, Inc.,143 So. 3d at 1143 (quoting Snider v. Continental Ins. Co., 519 So. 2d 12, 13 (Fla. 5th
DCA 1987) (“Although ‘attorney’s fees incurred in the defense of a claim
indemnified against are part of the damages allowable, . . . attorney’s fees
incurred in establishing the right to indemnification are not allowable.’”)); Am. & Foreign Ins. Co., v. Avis
Rent–A–Car Sys., Inc., 401 So. 2d 855 (Fla. 1st DCA 1981).
[241] Succar, 237 Fed. Appx. at 528–29 (citing Univ. Plaza Shopping Ctr., Inc. v. Stewart, 272 So. 2d 507,
511 (Fla. 1973)) (“For, example, a tenant’s agreement to indemnify the landlord
against ‘any and all claims’ does not clearly and unequivocally express an
intent to include claims by the tenant that result exclusively from the
negligence of the landlord.”).
[242] 387 So. 2d 523 (Fla. 4th
DCA 1980).
[243] Id.
[244] Id.
[245] Id.
[246] Id.at 1351.
[247] Id.
[248] Id.
[249] 757 So. 2d 1231, 1232
(Fla. 3d DCA 2000).
[250] Id.
[251] Id.
[252] Id.
[253] Id.
[254] Id.
[255] Id.
[256] §§ 57.105, 768.79, Fla.
Stat. (2019).
[257] § 57.105(1)(a).
[258] Albritton v. Ferrera, 913 So. 2d 5, 8-9 (Fla. 1st DCA 2005) (citing Couch v. Drew, 554 So. 2d 1185
(Fla. 1st DCA 1989); Wright v. Acierno,
437 So. 2d 242 (Fla. 5th DCA 1983)).
[259] Yang Enters. v. Georgalis, 988 So. 2d 1180, 1185 (Fla. 1st DCA
2008).
[260] § 768.79.
[261] Air Caledonie Intern. v. AAR Parts Trading, Inc., 315 F. Supp. 2d
1319 (S.D. Fla. 2004).
[262] Fla. R. Civ. P.
1.120(g).
[263] Tuttle/White Constructors, Inc. v. Montgomery Elevator Co., 385 So.
2d 98 (Fla. 5th DCA 1980); but see
Kritikos v. Andersen, 125 So. 3d 885, 886 (Fla. 4th DCA 2013).
[264] Hillsborough Cty. Aviation Auth. v. Cone Bros. Contracting Co., 285
So. 2d 619 (Fla. 2d DCA 1973).
[265] George Sollitt Const. Co. v. United States, 64 Fed. Cl. 229 (2005).
[266] Metric Const. Co., Inc. v. United States, 81 Fed. Cl. 804 (2008); Orlosky Inc. v. United States, 68 Fed.
Cl. 296 (2005).
[267] C. A. Davis, Inc. v. City of Miami, 400 So. 2d 536 (Fla. 3d DCA
1981); Southern Gulf Utilities, Inc. v.
Boca Ciega Sanitary Dist., 238 So. 2d 458 (Fla. 2d DCA 1970); Marriott Corp. v. Dasta Const. Co., 26
F.3d 1057 (11th Cir. 1994); U.S. for Use
and Benefit of Seminole Sheet Metal Co. v. SCI, Inc., 828 F.2d 671 (11th
Cir. 1987).
[268] Tiara Condo. Ass’n v. Marsh & McLennan Cos., 110 So. 3d 399
(Fla. 2013).
[269] See id. at 403.
[270] Id.
[271] Id.
[272] Id.
[273] Fla. Power & Light Co. v. Westinghouse Elec. Corp., 510 So. 2d
899, 901 (Fla. 1987).
[274] Tiara Condo. Assn, 110 So. 3d 399.
[275] Id. at 400.
[276] Id.
[277] Id. at 403.
[278] Id. at 405 (quoting Indem.
Ins. Co. v. Am. Aviation, Inc., 891 So. 2d 532, 541 (Fla. 2004)).
[279] Id. at 407.
[280] To add fuel to the fire,
both Westlaw and Lexis indicate the Casa
Clara Condominium Association. v. Charley Toppino & Sons, 620 So. 2d
1244 (Fla. 1993), opinion was receded from by the court in Tiara Condo. Assn, 110 So. 3d 399. This is an incorrect reading of
the Tiara opinion. See infra note 272.
[281] Casa Clara Condo. Assn. v. Charley Toppino & Sons, 620 So. 2d
1244, 1247 (Fla. 1993).
[282] Id. (internal citations omitted).
[283] Id. at 1246-47.
[284] Sensenbrenner v. Rust, Orling & Neale, Architects, Inc., 374
S.E.2d 55, 56 (1988).
[285] Id.
[286] Id.
[287] Id.
[288] Id.
[289] Id. at 58 (internal citations omitted) (court’s emphasis included).
[290] See also, e.g., Order on Parties’ Cross-Motions for Summary
Judgment, Central Park LV Condo. v.
Summit Contractors, No. 2010-CA-017748-0 (9th Jud. Cir. Orange Cnty., May
24, 2013); Order on Defendant’s Motion to Dismiss, PME Providence, LLC v. Am. Residential Const. Inc., No.
12-CA-121-11 (18th Jud. Cir. Seminole Cnty., Oct. 30, 2013); Order Granting
Defendant’s Motion to Dismiss, Siena at
Celebration Master Assoc. Inc. v. Winter Park Const. Co., No. 2009-CA-6474
(9th Jud. Cir. Osceola Cnty., Sept. 4, 2013), Amended Order Granting Defendant
Culligan International Company’s Motion for Final Summary Judgment, Epic Hotel, LLC v. DP Property Holding, LLC,
No. 11-08742-CA-03 (11th Jud. Cir. Miami-Dade Cnty., Aug. 14, 2014).
[291] Tiara Condo. Assn, 110 So. 3d at 400.
[292] Casa Clara Condo. Assn, 620 So. 2d at 1248.
[293] See Epic Hotel, LLC v. Culligan Int’l Co., 159 So. 3d 1014, 1015 (Fla.
3d DCA 2015) (upholding summary judgment granted relying upon the Casa Clara definition of a building as a
product after Tiara).
[294] See Tiara Condo. Assn, 110 So. 3d at 408 (Pariente, J.,
concurring).
[295] Id.
[296] Id. at 408-409
(citing See Lewis v. Guthartz, 428 So.2d 222, 224 (Fla.1982) (holding
that there must be a tort “distinguishable from or independent of [the] breach
of contract” in order for a party to bring a valid claim in tort based on a
breach in a contractual relationship); Elec. Sec. Sys. Corp. v. S. Bell Tel.
& Tel. Co., 482 So.2d 518, 519 (Fla. 3d DCA 1986) (“[A] breach of
contract, alone, cannot constitute a cause of action in tort…. It is only
when the breach of contract is attended by some additional conduct which
amounts to an independent tort that such breach can constitute negligence.”
(citations omitted))).
[297] Watkins Motor Lines, Inc. v. Underwriters at Interest, at Lloyds,
892 So. 2d 1143 (Fla. 3rd DCA 2005).
[298] § 687.01, Fla. Stat.
(2019).
[299] Id.
[300] § 768.72(1), Fla. Stat.
(2019).
[301] § 768.72(2).
[302] § 768.72(2)(a).
[303] § 768.72(2)(b).
[304] § 768.72.
[305] § 768.73, Fla. Stat.
(2019).
[306] § 768.73(1)(c).
[307] § 768.73(1)(b).
[308] § 768.73(1)(a).
[309] § 768.73(4).
[310] § 768.73(3).
[311] Pembroke v. Caudill, 37 So. 2d 538 (Fla. 1948); Hillsborough County Aviation Authority v.
Cone Bros. Contracting Co., 285 So. 2d 619 (Fla. 2d DCA 1973); Osceola County v. Bumble Bee Const., Inc.,
479 So. 2d 310 (Fla. 5th DCA 1985); Hyman
v. Cohen, 73 So. 2d 393 (Fla. 1954); Lefemine
v. Baron, 573 So. 2d 326 (Fla. 1991); Resnick
v. Uccello Immobilien GMBH, Inc., 227 F.3d 1347 (11th Cir. 2000); Rusniaczek v. Tableau Fine Art Group, Inc.,
139 So. 3d 355 (Fla. 3d DCA 2014).
[312] Refram v. Porter, 343 So. 2d 1343 (Fla. 2d DCA 1977).
[313] Hungerford Const. Co. v. Florida Citrus Exposition, Inc., 410 F.2d
1229 (5th Cir. 1969); Nicholas v. Miami
Burglar Alarm Co., 266 So. 2d 64 (Fla. 3d DCA 1972); Smith v. Newell, 20 So. 249 (1896).
[314] Hutchison v. Tompkins, 259 So. 2d 129 (Fla. 1972); Goldblatt v. C.P. Motion, Inc., 77 So.
3d 798 (Fla. 3d DCA 2011).
[315] Mineo v. Lakeside Village of Davie, LLC, 983 So. 2d 20 (Fla. 4th
DCA 2008); Lefemine v. Baron, 573 So.
2d 326 (Fla. 1991); Hyman v. Cohen,
73 So. 2d 393 (Fla. 1954); Goldblatt v.
C.P. Motion, Inc., 77 So. 3d 798 (Fla. 3d DCA 2011).
[316] Pembroke v. Caudill, 37 So. 2d 538 (1948); U.S. for Use and Ben. of Sunbeam Equipment Corp. v. Commercial Const.
Corp., 741 F.2d 326 (11th Cir. 1984); Multitech
Corp. v. St. Johns Bluff Inv. Corp., 518 So. 2d 427 (Fla. 1st DCA 1988).
[317] T.A.S. Heavy Equipment, Inc. v. Delint, Inc., 532 So. 2d 23 (Fla.
4th DCA 1988).
[318] Lefemine v. Baron, 573 So. 2d 326 (Fla. 1991); Cloud v. Schenck, 869 So. 2d 709 (Fla. 1st DCA 2004).
[319] Lefemine v. Baron, 573 So. 2d 326 (Fla. 1991).
[320] Hall Const. Co., Inc. v. Beynon, 507 So. 2d 1225 (Fla. 5th DCA
1987).
[321] Commercial Mech. Co. v. State for Use and Benefit of Am. Air Filter Co.,
260 So. 2d 540 (Fla. 1st DCA 1972).
[322] Concrete Sys., Inc. v. Fla. Elec. Co. of Orlando, 425 So. 2d 632
(Fla. 2d DCA 1983).
[323] In re Amendments to Florida Rule
of Civil Procedure 1.442, 47 Fla. L. Weekly S137, 1 (Fla. May 26, 2022).
[324] Id.
[325] Fla. R. Civ. P. 1.442 (c)(2)(C)
(2021).
[326] In re Amendments to Florida
Rule of Civil Procedure 1.442, 47 Fla. L. Weekly S137 at 1.
[327] Id.
[328] Id.
[329] Id.
[330] Id.
[331] Id.
[332] Kuhajda v. Borden Dairy Co.
of Ala., 202 So. 3d 391, 396 (Fla. 2016).
[333] Id.
[334] SB Holdings I, LLC, V.
Indian Harbor Insurance Company, 6:19-CV-668-PGB-DCI, 2022 WL 2317454, 2
(M.D. Fla. Apr. 1, 2022) (citing Fla. R. Civ. P. 1.442 (c)(2)(D) (2021)).
[335] Id.
[338] Id.
[339] Fla. R. Civ. P. 1.510 (c)(5).
[340] In re Amendments to Florida Rule
of Civil Procedure 1.510,
317 So. 3d at 74.
[341] Lloyd S. Meisels, P.A. v.
Dobrofsky,
4D21-2397, 2022 WL 2057777, 4 (Fla. 4th DCA June 8, 2022)
[342] Id. at 3.
[343] Id.
[344] Id. at 4. See Fla. R.
Civ. P. 1.510(c)(3).
[345]
Id. at 4.
[346] Bedford v. Doe, 880 F.3d 993, 996-97 (8th
Ci. 2018).
[347] Wease v. Ocwen Loan
Servicing, L.L.C., 915 f.3d 987,997 (5th. Cir. 2019).
[348] Bruce J. Berman & Peter D.
Webster, Berman’s Florida Civil Procedure § 1.510:5 (2020 ed.)
(describing Florida’s pre-amendment summary judgment standard).
[349] In re Amendments to Florida
Rule of Civil Procedure 1.510, 317 So. 3d at 77.
[350] Id.
[351] Id.
[352] Id. See also Jones
v. Ervolino, 47 Fla. L. Weekly D1090 (Fla. 3d DCA May 18, 2022) (ruling the
case be remanded because the trial court’s oral pronouncement and written order
contained insufficient specificity as to the reasons for granting the motion
for summary judgement.
[353] Spring Isle Cmty. Ass’n,
Inc. v. Herme Enterprises, Inc., 328 So. 3d 1120, 1121 (Fla. 5th DCA 2021).
[354] Id.
[355] Id.
[356] Id.
[357] Id.
[358] §
95.11, Fla. Stat. Ann. (3)(c). Note that Section 95.11(3)(c) also creates a
four-year statute of limitations on these claims. Like the ten-year repose
clause, the four-year statute of limitations begins to run from the accrual of
the last of these same four specified events, except for latent defects, to
which the time period begins running from the date the defect was discovered or
should have been discovered with the exercise of due diligence.
[359] Spring Isle Cmty. Ass’n,
Inc., 328 So. 3d at 1122.
[360] Id.
[361] Id.
[362] Id.
[363] Id. at 1123.
[364] Id.
[365] Id.
[366] Id. Because Pulte was
the developer and tract owner, it was also the owner of record of each unit
before they were sold to the first homebuyers. Further, there were no issues of
abandonment. Thus, the only two remaining triggering events that were potentially
applicable were that of completion of the contract or issuance of the
certificate of occupancy.
[367] Id.
[368] Id.
[369] Id.
[370] Id.
[371] Id.
[372] §553.70, Fla. Stat. et
seq.
[373] §553.84, Fla. Stat.
[374] Id.
[375] Id.